United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Texas (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown143,201 MW
Active in queue3,201 MW14 requests
Agreement signed1,107 MW5 requests
Withdrawn246,944 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

14 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Eagle Pines Gas
Gas Β· FGE Power
1,174 MWIn study Cherokee, TXERCOT Mar 2015target 2028
Priddy Wind
Onshore wind Β· ENGIE North America
302 MWAgreement signed Mills, TXERCOT Jan 2015target 2026
Big Sampson Wind
Onshore wind Β· Big Sampson Wind Project, LLC
265 MWAgreement signed Crockett, TXERCOT May 2015target 2026
Morada Del Sol Solar
Solar Β· First Solar
245 MWPaused / redesign Upton, TXERCOT Mar 2015target 2020
Coyote Wind
Onshore wind Β· Coyote Wind
243 MWAgreement signed Scurry, TXERCOT Apr 20152021
Grandview 4 Phase A Wind
Onshore wind
201 MWPaused / redesign Carson, TXERCOT Nov 2015
Loma Pinta Wind
Onshore wind Β· Enerverse
197 MWAgreement signed La Salle, TXERCOT May 2015target 2026
Whatley Solar
Solar Β· Invenergy
150 MWPaused / redesign Andrews, TXERCOT May 2015target 2020
Wake Solar
Solar Β· Invenergy
150 MWPaused / redesign Crosby, TXERCOT Jul 2015target 2021
Solar project J483, Liberty County
Solar
100 MWAgreement signed Liberty, TXMISO Sep 20152024
Owego Solar
Solar Β· Hecate Energy
74.0 MWPaused / redesign Pecos, TXERCOT Apr 2015target 2020
Chatee Solar
Solar Β· Hecate Energy
57.0 MWPaused / redesign Pecos, TXERCOT Apr 2015target 2020
Hecate Solar
Solar Β· Hecate Energy
33.0 MWPaused / redesign Brewster, TXERCOT Mar 2015target 2020
Mirage
Gas
11.0 MWPaused / redesign Harris, TXERCOT Feb 2015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)