United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Texas (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown164,201 MW
Active in queue116.3 GW402 requests
Agreement signed4,428 MW22 requests
Withdrawn164,201 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

16 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Pi1000G
Gas
1,034 MWWithdrawn / abandoned El Paso, TXWest Jun 2025target 2028
Solar project GEN-2024-307, Houston County
Solar
455 MWWithdrawn / abandoned Houston, TXSPP Mar 2025target 2028
Solar project GEN-2024-098, Wilbarger County
Solar
400 MWWithdrawn / abandoned Wilbarger, TXSPP Mar 2025target 2031
Onshore wind project GEN-2024-100, Castro County
Onshore wind
300 MWWithdrawn / abandoned Castro, TXSPP Mar 2025target 2031
Solar project GEN-2024-363, Deaf Smith County
Solar
300 MWWithdrawn / abandoned Deaf Smith, TXSPP Mar 2025target 2029
Battery storage project J4104, Houston County
Battery storage
250 MWWithdrawn / abandoned Houston, TXMISO Oct 2025target 2030
Briggs Storage II
Battery storage Β· Briggs Solar, LLC
250 MWWithdrawn / abandoned Haskell, TXERCOT Jun 2025target 2027
Solar project GEN-2024-155, Cherokee County
Solar
200 MWWithdrawn / abandoned Cherokee, TXSPP Mar 2025target 2029
Onshore wind project J3972, Liberty County
Onshore wind
200 MWWithdrawn / abandoned Liberty, TXMISO Mar 2025target 2029
Solar project GEN-2024-106, Lamb County
Solar
200 MWWithdrawn / abandoned Lamb, TXSPP Mar 2025target 2031
Battery storage project GEN-2024-356, Lubbock County
Battery storage
199 MWWithdrawn / abandoned Lubbock, TXSPP Mar 2025target 2030
Solar project GEN-2024-149, Lamb County
Solar
196 MWWithdrawn / abandoned Lamb, TXSPP Mar 2025target 2032
Solar project GEN-2024-148, Lamb County
Solar
100 MWWithdrawn / abandoned Lamb, TXSPP Mar 2025target 2032
Zircon BESS
Battery storage Β· Zircon BESS LLC
80.4 MWWithdrawn / abandoned La Salle, TXERCOT Jan 2025target 2028
Delek Big Spring Solar
Solar Β· TotalEnergies Distributed Generation USA, LLC
21.4 MWWithdrawn / abandoned Howard, TXERCOT Feb 2025target 2027
Delek Big Spring Storage
Battery storage Β· TotalEnergies Distributed Generation USA, LLC
15.3 MWWithdrawn / abandoned Howard, TXERCOT Feb 2025target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)