United States โ€บ Grid โ€บ Interconnection queues โ€บ Pennsylvania

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Pennsylvania

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,354164.3 GW
Active in queue12.5 GW231 requests
Agreement signed2,306 MW58 requests
Withdrawn1,354164.3 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,354 requests ยท page 1 of 28
ProjectCapacityStatusLocationRegionQueuedOnline
Coal project R67, Beaver County
Coal
2,510 MWWithdrawn / abandoned Beaver, PAPJM Jan 2007target 1980
Gas project AH1-675, Columbia County
Gas ยท Invitium Energy, LLC
2,175 MWWithdrawn / abandoned Columbia, PAPJM target 2030
Hatfield Ferry, Units 1, 2, and 3
Coal
1,710 MWWithdrawn / abandoned Greene, PAPJM Oct 2014target 2019
Gas project AH1-674, Beaver County
Gas ยท Shippingport Power Station, LLC
1,700 MWWithdrawn / abandoned Beaver, PAPJM target 2028
Gas project E17_W26
Gas
1,595 MWWithdrawn / abandoned PAPJM Nov 2000target 2005
Gas project AB1-003, Indiana County
Gas
1,474 MWWithdrawn / abandoned Indiana, PAPJM May 2015target 2019
Gas project AH1-689, Columbia County
Gas ยท Invitium Energy, LLC
1,450 MWWithdrawn / abandoned Columbia, PAPJM target 2030
Gas project AH1-688, Columbia County
Gas ยท Invitium Energy, LLC
1,450 MWWithdrawn / abandoned Columbia, PAPJM target 2030
Gas project A40, Dauphin County
Gas
1,271 MWWithdrawn / abandoned Dauphin, PAPJM Jan 1999
Gas project AC2-118, Armstrong County
Gas
1,200 MWWithdrawn / abandoned Armstrong, PAPJM Mar 2017target 2021
Gas project G33, York County
Gas
1,200 MWWithdrawn / abandoned York, PAPJM May 2001
Gas project S105, Bucks County
Gas
1,200 MWWithdrawn / abandoned Bucks, PAPJM Jul 2007target 2011
Gas project F05_W38
Gas
1,200 MWWithdrawn / abandoned PAPJM Jan 2001target 2004
Renaissance Energy Center
Gas
1,140 MWWithdrawn / abandoned Greene, PAPJM Oct 2016target 2021
Gas project AC2-025, Greene County
Gas
1,140 MWWithdrawn / abandoned Greene, PAPJM Jan 2017target 2022
Gas project AA2-109, Lancaster County
Gas
1,100 MWWithdrawn / abandoned Lancaster, PAPJM Apr 2015target 2019
Gas project Y2-080, Westmoreland County
Gas
1,065 MWWithdrawn / abandoned Westmoreland, PAPJM Oct 2012target 2017
Gas project AB1-153, Adams County
Gas
1,062 MWWithdrawn / abandoned Adams, PAPJM Oct 2015target 2020
Gas project H14, York County
Gas
1,060 MWWithdrawn / abandoned York, PAPJM Nov 2001target 2005
Gas project AA2-182, Snyder County
Gas
1,030 MWWithdrawn / abandoned Snyder, PAPJM Apr 2015target 2019
Beech Hollow Energy Center
Gas
1,025 MWWithdrawn / abandoned Washington, PAPJM Sep 2015target 2023
Gas project X1-013, Lebanon County
Gas
1,018 MWWithdrawn / abandoned Lebanon, PAPJM Feb 2011target 2015
Gas project A25, Northampton County
Gas
1,000 MWWithdrawn / abandoned Northampton, PAPJM Oct 1998
Gas project Y1-015, Lawrence County
Gas
1,000 MWWithdrawn / abandoned Lawrence, PAPJM Feb 2012target 2015
Gas project AB1-175, Clearfield County
Gas
989 MWWithdrawn / abandoned Clearfield, PAPJM Oct 2015target 2020
Gas project U4-013, Lebanon County
Gas
950 MWWithdrawn / abandoned Lebanon, PAPJM Nov 2008target 2011
Gas project U1-057, Lebanon County
Gas
950 MWWithdrawn / abandoned Lebanon, PAPJM Mar 2008target 2011
Coal project R94, Luzerne County
Coal
940 MWWithdrawn / abandoned Luzerne, PAPJM Jan 2007target 2011
Coal project R95, Luzerne County
Coal
940 MWWithdrawn / abandoned Luzerne, PAPJM Jan 2007target 2011
Coal project R26, Northumberland County
Coal
940 MWWithdrawn / abandoned Northumberland, PAPJM Oct 2006target 2011
Coal project R28, Luzerne County
Coal
940 MWWithdrawn / abandoned Luzerne, PAPJM Oct 2006target 2011
Coal project R24, Luzerne County
Coal
940 MWWithdrawn / abandoned Luzerne, PAPJM Oct 2006target 2011
Gas project B21, Berks County
Gas
925 MWWithdrawn / abandoned Berks, PAPJM Aug 1999
Gas project S116, Berks County
Gas
912 MWWithdrawn / abandoned Berks, PAPJM Jul 2007target 2011
Gas project T38, Delaware County
Gas
900 MWWithdrawn / abandoned Delaware, PAPJM Sep 2007target 2012
Gas project T179, Northampton County
Gas
873 MWWithdrawn / abandoned Northampton, PAPJM Jan 2008target 2012
Gas project B25, Chester County
Gas
870 MWWithdrawn / abandoned Chester, PAPJM Sep 1999
Gas project I08, Chester County
Gas
870 MWWithdrawn / abandoned Chester, PAPJM Apr 2002target 2005
Nuclear project J649, Dauphin County
Nuclear
829 MWWithdrawn / abandoned Dauphin, PAMISO Jun 2016target 2057
Gas project Y1-070, Lawrence County
Gas
825 MWWithdrawn / abandoned Lawrence, PAPJM Apr 2012target 2017
Coal project R04, Snyder County
Coal
817 MWWithdrawn / abandoned Snyder, PAPJM Sep 2006target 2011
Other project AE2-032, Lackawanna County
Other
811 MWWithdrawn / abandoned Lackawanna, PAPJM Jan 2019
Gas project Z2-026, Berks County
Gas
800 MWWithdrawn / abandoned Berks, PAPJM Feb 2014target 2018
Gas project U2-053, Northampton County
Gas
800 MWWithdrawn / abandoned Northampton, PAPJM Jun 2008target 2012
Nuclear project R01, Montour County
Nuclear
800 MWWithdrawn / abandoned Montour, PAPJM Aug 2006target 2018
Gas project X4-020, York County
Gas
800 MWWithdrawn / abandoned York, PAPJM Nov 2011target 2017
Nuclear project R02, Luzerne County
Nuclear
800 MWWithdrawn / abandoned Luzerne, PAPJM Aug 2006target 2018
Gas project A38, Crawford County
Gas
765 MWWithdrawn / abandoned Crawford, PAPJM Jan 1999
Gas project A41, Dauphin County
Gas
765 MWWithdrawn / abandoned Dauphin, PAPJM Jan 1999
Gas project B18, Chester County
Gas
750 MWWithdrawn / abandoned Chester, PAPJM Jul 1999
Page 1 of 28

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)