United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Oklahoma (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown234,431 MW
Active in queue2,034 MW9 requests
Agreement signed1,005 MW3 requests
Withdrawn234,431 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

23 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GI-105, Osage County
Gas
460 MWWithdrawn / abandoned Osage, OKSoutheast Jul 2022target 2025
Other project GEN-2022-GR2, Oklahoma County
Other
400 MWWithdrawn / abandoned Oklahoma, OKSPP Aug 2022target 2027
Solar project GEN-2022-011, Tillman County
Solar
374 MWWithdrawn / abandoned Tillman, OKSPP Jun 20222025
Onshore wind project GI-112, Craig County
Onshore wind
300 MWWithdrawn / abandoned Craig, OKSoutheast Nov 2022target 2026
Onshore wind project GEN-2022-092, Nowata County
Onshore wind
299 MWWithdrawn / abandoned Nowata, OKSPP Nov 2022target 2026
Solar + storage project GI-108, Craig County
Solar + storage
250 MWWithdrawn / abandoned Craig, OKSoutheast Aug 2022target 2025
Onshore wind project GEN-2022-048, Woodward County
Onshore wind
250 MWWithdrawn / abandoned Woodward, OKSPP Jun 20222025
Solar project GEN-2022-040, Stephens County
Solar
250 MWWithdrawn / abandoned Stephens, OKSPP Jun 20222025
Onshore wind project GEN-2022-085, Okfuskee County
Onshore wind
241 MWWithdrawn / abandoned Okfuskee, OKSPP Nov 20222025
Onshore wind project GEN-2022-074, Mcintosh County
Onshore wind
221 MWWithdrawn / abandoned Mcintosh, OKSPP Sep 20222025
Solar project GEN-2022-072, Mayes County
Solar
181 MWWithdrawn / abandoned Mayes, OKSPP Aug 2022target 2028
Solar project GEN-2022-042, Carter County
Solar
174 MWWithdrawn / abandoned Carter, OKSPP Jun 20222025
Battery storage project GEN-2022-091, Mccurtain County
Battery storage
150 MWWithdrawn / abandoned Mccurtain, OKSPP Nov 2022target 2026
Solar project GEN-2022-090, Mccurtain County
Solar
150 MWWithdrawn / abandoned Mccurtain, OKSPP Nov 2022target 2026
Solar project GEN-2022-003, Jackson County
Solar
125 MWWithdrawn / abandoned Jackson, OKSPP May 2022target 2026
Battery storage project GEN-2022-019, Tillman County
Battery storage
100 MWWithdrawn / abandoned Tillman, OKSPP Jun 20222025
Battery storage project GEN-2022-021, Tillman County
Battery storage
100 MWWithdrawn / abandoned Tillman, OKSPP Jun 20222025
Battery storage project GEN-2022-SR5, Dewey County
Battery storage
85.0 MWWithdrawn / abandoned Dewey, OKSPP May 20222022
Battery storage project GEN-2023-SR2
Battery storage
85.0 MWWithdrawn / abandoned OKSPP Nov 20222024
Battery storage project GEN-2022-064, Major County
Battery storage
80.0 MWWithdrawn / abandoned Major, OKSPP Jul 2022target 2027
Battery storage project GEN-2022-060, Osage County
Battery storage
55.0 MWWithdrawn / abandoned Osage, OKSPP Jun 2022target 2027
Battery storage project GEN-2022-SR6, Kay County
Battery storage
50.0 MWWithdrawn / abandoned Kay, OKSPP May 20222022
Battery storage project GEN-2023-SR3, Kay County
Battery storage
50.0 MWWithdrawn / abandoned Kay, OKSPP Dec 20222024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)