United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
BATTERY STORAGE Β· SPPBattery storage project GEN-2023-SR2
Battery storage project GEN-2023-SR2 is a 85.0 MW battery storage request withdrawn in the SPP interconnection queue, connecting to OGE.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2022 (completed)
- Withdrawn / abandonedOct 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingDec 2024 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2023-SR2
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OGE
- Connection point (POI)
- Minco 345 kV Substation
- Location
- Oklahoma
- Technology
- Battery: 85.0 MW
- Total requested
- 85.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 30 November 2022
- Proposed online date
- December 2024
- Came online
- December 2024
- Withdrawn
- October 2023
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem