United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
BATTERY STORAGE Β· SPPBattery storage project GEN-2022-060, Osage County
Battery storage project GEN-2022-060, Osage County is a 55.0 MW battery storage request withdrawn in the SPP interconnection queue, in Osage County, Oklahoma, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2022 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2022-060
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Hwy 20 138 kV Substation
- Location
- Osage County, Oklahoma
- Technology
- Battery: 55.0 MW
- Total requested
- 55.0 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 23 June 2022
- Proposed online date
- April 2027
- Withdrawn
- November 2023
Location
Marker shows the centre of Osage County; the queue data does not give exact sites.
Other requests in Osage County
- Gas project GI-105, Osage CountyGas Β· 460 MW Β· withdrawn
- Onshore wind project GEN-2016-127, Osage CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GI-63, Osage CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GI-59, Osage CountyOnshore wind Β· 200 MW Β· withdrawn
- Battery storage project GEN-2022-129, Osage CountyBattery storage Β· 200 MW Β· withdrawn
- Onshore wind project GI-29, Osage CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GI-57, Osage CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GEN-2011-006, Osage CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project GI-47, Osage CountyOnshore wind Β· 151 MW Β· withdrawn
- Onshore wind project GEN-2008-038, Osage CountyOnshore wind Β· 144 MW Β· withdrawn
- Onshore wind project GI-52, Osage CountyOnshore wind Β· 144 MW Β· withdrawn
- Onshore wind project GEN-2012-027, Osage CountyOnshore wind Β· 136 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem