Battery storage project GEN-2022-060, Osage County

Battery storage project GEN-2022-060, Osage County is a 55.0 MW battery storage request withdrawn in the SPP interconnection queue, in Osage County, Oklahoma, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2022 (completed)
  2. Withdrawn / abandonedNov 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2022-060
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
AEP
Connection point (POI)
Hwy 20 138 kV Substation
Location
Osage County, Oklahoma
Technology
Battery: 55.0 MW
Total requested
55.0 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
23 June 2022
Proposed online date
April 2027
Withdrawn
November 2023

Location

Marker shows the centre of Osage County; the queue data does not give exact sites.