United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
BATTERY STORAGE Β· SPPBattery storage project GEN-2023-SR3, Kay County
Battery storage project GEN-2023-SR3, Kay County is a 50.0 MW battery storage request withdrawn in the SPP interconnection queue, in Kay County, Oklahoma, connecting to OGE.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2022 (completed)
- Withdrawn / abandonedApr 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingDec 2024 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2023-SR3
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OGE
- Connection point (POI)
- Nardin 69 kV Substation
- Location
- Kay County, Oklahoma
- Technology
- Battery: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 15 December 2022
- Proposed online date
- December 2024
- Came online
- December 2024
- Withdrawn
- April 2023
Location
Marker shows the centre of Kay County; the queue data does not give exact sites.
Other requests in Kay County
- Battery storage project GEN-2018-072, Kay CountyBattery storage Β· 151 MW Β· agreement signed
- Battery storage project GEN-2018-071, Kay CountyBattery storage Β· 151 MW Β· agreement signed
- Onshore wind project GEN-2016-071, Kay CountyOnshore wind Β· 64.6 MW Β· agreement signed
- Onshore wind project GEN-2024-GR6, Kay CountyOnshore wind Β· 300 MW Β· in study
- Gas project GEN-2024-334, Kay CountyGas Β· 124 MW Β· in study
- Battery storage project GEN-2024-SR17, Kay CountyBattery storage Β· 50.0 MW Β· in study
- Onshore wind project GEN-2012-032, Kay CountyOnshore wind Β· 299 MW Β· built
- Onshore wind project GEN-2015-001, Kay CountyOnshore wind Β· 200 MW Β· built
- Onshore wind project GEN-2015-034, Kay CountyOnshore wind Β· 200 MW Β· built
- Onshore wind project GEN-2016-022, Kay CountyOnshore wind Β· 152 MW Β· built
- Gas project GEN-2012-041, Kay CountyGas Β· 122 MW Β· built
- Onshore wind project GEN-2009-025, Kay CountyOnshore wind Β· 59.8 MW Β· built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem