Withdrawn queue requests in Ohio (2012 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown122,147 MW
Active in queue0.0 MW0 requests
Agreement signed0.0 MW0 requests
Withdrawn122,147 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

12 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project Y2-085, Carroll County
Gas
1,050 MWWithdrawn / abandoned Carroll, OHPJM Oct 2012target 2017
Gas project Y1-036, Lake County
Gas
462 MWWithdrawn / abandoned Lake, OHPJM Mar 2012target 2017
Gas project Y1-035, Lake County
Gas
462 MWWithdrawn / abandoned Lake, OHPJM Mar 2012target 2017
Onshore wind project Y1-030, Wyandot County
Onshore wind
100 MWWithdrawn / abandoned Wyandot, OHPJM Feb 2012target 2015
Gas project Y2-053, Wood County
Gas
35.0 MWWithdrawn / abandoned Wood, OHPJM Aug 2012target 2016
Solar project Y1-023
Solar
20.0 MWWithdrawn / abandoned OHPJM Feb 2012target 2013
Solar project Y1-074, Summit County
Solar
7.8 MWWithdrawn / abandoned Summit, OHPJM Apr 2012target 2013
Berkshire 3.4kV
Battery storage
4.0 MWWithdrawn / abandoned Delaware, OHPJM Apr 2012target 2015
Solar project Y1-024
Solar
3.0 MWWithdrawn / abandoned OHPJM Feb 2012target 2013
Other project Y2-057, Wyandot County
Other
3.0 MWWithdrawn / abandoned Wyandot, OHPJM Aug 2012target 2013
Solar project Y2-091, Lucas County
Solar
0.3 MWWithdrawn / abandoned Lucas, OHPJM Oct 2012
Solar project Y2-092, Wood County
Solar
0.3 MWWithdrawn / abandoned Wood, OHPJM Oct 2012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)