๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues โ€บ North Carolina

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in North Carolina (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7511.3 GW
Active in queue11.3 GW75 requests
Agreement signed92.8 MW3 requests
Withdrawn81,156 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

75 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 977726, Rowan County
Gas
1,620 MWIn study Rowan, NCSoutheast Jun 2025
Gas project 977731, Davidson County
Gas
1,395 MWIn study Davidson, NCSoutheast Jun 2025
Gas project 977454, Anson County
Gas
990 MWIn study Anson, NCSoutheast Jun 2025
Gas project 977564, Cleveland County
Gas
810 MWIn study Cleveland, NCSoutheast Jun 2025
Gas project 977444, Anson County
Gas
495 MWIn study Anson, NCSoutheast Jun 2025
Other project 977298, Wake County
Other
300 MWIn study Wake, NCSoutheast Jun 2025
Other project PP00041, Wake County
Other
300 MWIn study Wake, NCSoutheast Aug 2025target 2030
Other project PP00046, Richmond County
Other
275 MWIn study Richmond, NCSoutheast Aug 2025target 2029
Gas project 977773, Richmond County
Gas
260 MWIn study Richmond, NCSoutheast Jun 2025
Battery storage project PP00027, Wayne County
Battery storage
260 MWIn study Wayne, NCSoutheast Apr 2025target 2028
Battery storage project 977301, Gaston County
Battery storage
250 MWIn study Gaston, NCSoutheast Jun 2025
Battery storage project 977286, Stokes County
Battery storage
250 MWIn study Stokes, NCSoutheast Jun 2025
Other project PP00048, Onslow County
Other
199 MWIn study Onslow, NCSoutheast Aug 2025target 2030
Other project 977328, Robeson County
Other
199 MWIn study Robeson, NCSoutheast Jun 2025
Battery storage project 977397, Onslow County
Battery storage
199 MWIn study Onslow, NCSoutheast Jun 2025
Battery storage project 977296, Durham County
Battery storage
199 MWIn study Durham, NCSoutheast Jun 2025
Other project PP00047, Robeson County
Other
199 MWIn study Robeson, NCSoutheast Aug 2025target 2030
Other project PP00049, Onslow County
Other
199 MWIn study Onslow, NCSoutheast Aug 2025target 2030
Battery storage project 977359, Onslow County
Battery storage
199 MWIn study Onslow, NCSoutheast Jun 2025
Battery storage project 977299, Gaston County
Battery storage
199 MWIn study Gaston, NCSoutheast Jun 2025
Battery storage project PP00028, Wayne County
Battery storage
150 MWIn study Wayne, NCSoutheast Apr 2025target 2028
Other project PP00040, Durham County
Other
150 MWIn study Durham, NCSoutheast Aug 2025target 2030
Solar project AH1-040, Washington County
Solar ยท ACE Development Company, LLC
150 MWIn study Washington, NCPJM Feb 2025target 2025
Other project 977263, Durham County
Other
150 MWIn study Durham, NCSoutheast Jun 2025
Battery storage project 976971, Iredell County
Battery storage
99.0 MWIn study Iredell, NCSoutheast Jun 2025
Battery storage project PP00026, Robeson County
Battery storage
99.0 MWIn study Robeson, NCSoutheast Apr 2025target 2029
Gas project 977565, Cleveland County
Gas
88.4 MWIn study Cleveland, NCSoutheast Jun 2025
Other project PP00043, Jones County
Other
80.0 MWIn study Jones, NCSoutheast Aug 2025target 2029
Other project PP00035, Wilson County
Other
80.0 MWIn study Wilson, NCSoutheast Jun 2025target 2029
Other project PP00051, Duplin County
Other
80.0 MWIn study Duplin, NCSoutheast Aug 2025target 2029
Other project PP00042, Granville County
Other
80.0 MWIn study Granville, NCSoutheast Jun 2025target 2027
Other project PP00044, Duplin County
Other
80.0 MWIn study Duplin, NCSoutheast Aug 2025target 2029
Solar project 977272, Wayne County
Solar
80.0 MWIn study Wayne, NCSoutheast Jun 2025
Solar project 977914, Columbus County
Solar
80.0 MWIn study Columbus, NCSoutheast Jun 2025
Solar project AG2-522, Warren County
Solar ยท Horizon Solar East, LLC
80.0 MWIn study Warren, NCPJM Feb 2025target 2025
Solar project 977882, Cumberland County
Solar
74.9 MWIn study Cumberland, NCSoutheast Jun 2025
Solar project 977832, Granville County
Solar
74.9 MWIn study Granville, NCSoutheast Jun 2025
Solar project AG2-382, Bertie County
Solar ยท Merry Hill PV I, LLC
70.0 MWIn study Bertie, NCPJM Feb 2025target 2024
Other project PP00036, Robeson County
Other
70.0 MWIn study Robeson, NCSoutheast Jul 2025target 2028
Other project PP00045, Lenoir County
Other
70.0 MWIn study Lenoir, NCSoutheast Aug 2025target 2029
Other project PP00037, Wayne County
Other
67.0 MWIn study Wayne, NCSoutheast Jul 2025target 2029
Other project PP00050, Cumberland County
Other
65.0 MWIn study Cumberland, NCSoutheast Sep 2025target 2029
Other project PP00038, Nash County
Other
50.0 MWIn study Nash, NCSoutheast Jul 2025target 2029
Solar project 977831, Hoke County
Solar
49.9 MWIn study Hoke, NCSoutheast Jun 2025
Gas project PP00013, Richmond County
Gas
46.8 MWAgreement signed Richmond, NCSoutheast Apr 2025target 2025
Solar project AH1-271, Bertie County
Solar ยท Merry Hill PV I, LLC
40.0 MWIn study Bertie, NCPJM Feb 2025target 2024
Gas project PP00014, Richmond County
Gas
35.0 MWIn study Richmond, NCSoutheast Apr 2025target 2026
Coal project 978035, Forsyth County
Coal
30.0 MWIn study Forsyth, NCSoutheast May 2025
Coal project 978034, Forsyth County
Coal
30.0 MWIn study Forsyth, NCSoutheast May 2025
Gas project PP00012, Wayne County
Gas
26.0 MWAgreement signed Wayne, NCSoutheast Apr 2025target 2025
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)