Withdrawn queue requests in Nevada (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6030.8 GW
Active in queue14.9 GW39 requests
Agreement signed839 MW4 requests
Withdrawn6030.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

60 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Ashton Energy Center
Solar + storage
2,049 MWWithdrawn / abandoned Nye, NVCAISO Apr 2023target 2032
Chance Solar
Solar + storage
1,790 MWWithdrawn / abandoned Nye, NVCAISO Apr 2023target 2028
Solar + storage project Company PM, Esmeralda County
Solar + storage
1,500 MWWithdrawn / abandoned Esmeralda, NVWest Mar 2023target 2027
Amargosa SEZ
Solar + storage
1,019 MWWithdrawn / abandoned Nye, NVCAISO Apr 2023target 2030
Solar + storage project Company OZ, Esmeralda County
Solar + storage
1,000 MWWithdrawn / abandoned Esmeralda, NVWest Jan 2023target 2028
Solar + storage project Company PB, Esmeralda County
Solar + storage
1,000 MWWithdrawn / abandoned Esmeralda, NVWest Jan 2023target 2026
Solar + storage project Company 240, Nye County
Solar + storage
1,000 MWWithdrawn / abandoned Nye, NVWest Jan 2023target 2026
Wind + storage project Company QI, Esmeralda County
Wind + storage
960 MWWithdrawn / abandoned Esmeralda, NVWest Sep 2023target 2027
White Oak Solar
Solar + storage
813 MWWithdrawn / abandoned Nye, NVCAISO Apr 2023target 2029
Other project Q99, White Pine County
Other ยท Intermountain Power Agency
800 MWWithdrawn / abandoned White Pine, NVWest Feb 2023target 2029
Cathedral
Solar + storage
722 MWWithdrawn / abandoned Nye, NVCAISO Apr 2023target 2031
Onyx
Solar + storage
706 MWWithdrawn / abandoned Clark, NVCAISO Apr 2023target 2030
Solar + storage project Company 236, Nye County
Solar + storage
600 MWWithdrawn / abandoned Nye, NVWest Jan 2023target 2026
Solar + storage project Company 245, Nye County
Solar + storage
600 MWWithdrawn / abandoned Nye, NVWest Mar 2023target 2030
Reed Meadow
Battery storage
566 MWWithdrawn / abandoned Clark, NVCAISO Apr 2023target 2031
Solar + storage project Company OG, Lander County
Solar + storage
550 MWWithdrawn / abandoned Lander, NVWest Jan 2023target 2028
Solar + storage project Company 234, Nye County
Solar + storage
540 MWWithdrawn / abandoned Nye, NVWest Jan 2023target 2026
Grapevine 2
Battery storage
505 MWWithdrawn / abandoned Clark, NVCAISO Apr 2023target 2028
Solar + storage project Company PA, Esmeralda County
Solar + storage
500 MWWithdrawn / abandoned Esmeralda, NVWest Jan 2023target 2026
Solar + storage project Company 247, Nye County
Solar + storage
500 MWWithdrawn / abandoned Nye, NVWest Mar 2023target 2027
Solar + storage project Company PC, Lander County
Solar + storage
500 MWWithdrawn / abandoned Lander, NVWest Jan 2023target 2028
Solar + storage project Company PT, Esmeralda County
Solar + storage
500 MWWithdrawn / abandoned Esmeralda, NVWest Mar 2023target 2028
Solar + storage project Company 239, Nye County
Solar + storage
500 MWWithdrawn / abandoned Nye, NVWest Jan 2023target 2026
Battery storage project Company OO, Esmeralda County
Battery storage
500 MWWithdrawn / abandoned Esmeralda, NVWest Jan 2023target 2028
Solar + storage project Company OQ, Lander County
Solar + storage
500 MWWithdrawn / abandoned Lander, NVWest Jan 2023target 2035
Solar + storage project Company 259, Nye County
Solar + storage
500 MWWithdrawn / abandoned Nye, NVWest Sep 2023target 2027
Solar + storage project Company PS, Esmeralda County
Solar + storage
500 MWWithdrawn / abandoned Esmeralda, NVWest Mar 2023target 2027
Solar + storage project Company PX, Esmeralda County
Solar + storage
500 MWWithdrawn / abandoned Esmeralda, NVWest Mar 2023target 2028
Solar + storage project Company OR, Lander County
Solar + storage
500 MWWithdrawn / abandoned Lander, NVWest Jan 2023target 2035
Solar + storage project Company OM, Esmeralda County
Solar + storage
500 MWWithdrawn / abandoned Esmeralda, NVWest Jan 2023target 2028
Battery storage project Company PV, Eureka County
Battery storage
500 MWWithdrawn / abandoned Eureka, NVWest Mar 2023target 2028
Solar + storage project Company ON, Esmeralda County
Solar + storage
500 MWWithdrawn / abandoned Esmeralda, NVWest Jan 2023target 2028
Solar + storage project Company OL, Esmeralda County
Solar + storage
500 MWWithdrawn / abandoned Esmeralda, NVWest Jan 2023target 2028
Solar + storage project Company PF, Elko County
Solar + storage
460 MWWithdrawn / abandoned Elko, NVWest Feb 2023target 2026
Solar + storage project Company PN, Lander County
Solar + storage
450 MWWithdrawn / abandoned Lander, NVWest Mar 2023target 2026
Solar + storage project Company OK, Esmeralda County
Solar + storage
420 MWWithdrawn / abandoned Esmeralda, NVWest Jan 2023target 2026
Solar + storage project Company 246, Nye County
Solar + storage
400 MWWithdrawn / abandoned Nye, NVWest Mar 2023target 2030
Solar + storage project Company PU, Humboldt County
Solar + storage
400 MWWithdrawn / abandoned Humboldt, NVWest Mar 2023target 2027
Solar + storage project Company PW, Esmeralda County
Solar + storage
400 MWWithdrawn / abandoned Esmeralda, NVWest Mar 2023target 2028
Solar + storage project Company 235, Nye County
Solar + storage
370 MWWithdrawn / abandoned Nye, NVWest Jan 2023target 2026
Hiko
Battery storage
360 MWWithdrawn / abandoned Clark, NVCAISO Apr 2023target 2031
Solar + storage project Company PP, Eureka County
Solar + storage
350 MWWithdrawn / abandoned Eureka, NVWest Mar 2023target 2025
Onshore wind project Company 244, Nye County
Onshore wind
308 MWWithdrawn / abandoned Nye, NVWest Mar 2023target 2027
Solar + storage project Company OH, Lander County
Solar + storage
300 MWWithdrawn / abandoned Lander, NVWest Jan 2023target 2028
Solar + storage project Company QB, Pershing County
Solar + storage
300 MWWithdrawn / abandoned Pershing, NVWest Mar 2023target 2027
Solar + storage project Company 249, Clark County
Solar + storage
250 MWWithdrawn / abandoned Clark, NVWest Mar 2023target 2026
Battery storage project Company 243, Clark County
Battery storage
200 MWWithdrawn / abandoned Clark, NVWest Mar 2023target 2025
Solar + storage project Company PY, White Pine County
Solar + storage
200 MWWithdrawn / abandoned White Pine, NVWest Mar 2023target 2027
Solar + storage project Company QE, Lyon County
Solar + storage
200 MWWithdrawn / abandoned Lyon, NVWest May 2023target 2026
Solar + storage project Company QA, Lander County
Solar + storage
200 MWWithdrawn / abandoned Lander, NVWest Mar 2023target 2026
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)