United States βΊ Grid βΊ Interconnection queues βΊ Nevada
SOLAR + STORAGE Β· WESTSolar + storage project Company PF, Elko County
Solar + storage project Company PF, Elko County is a 460 MW solar + storage request withdrawn in the West interconnection queue, in Elko County, Nevada, connecting to NV Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- Company PF
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- NV Energy
- Location
- Elko County, Nevada
- Technology
- Solar: 460 MW Β· Battery
- Total requested
- 460 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 6 February 2023
- Proposed online date
- January 2026
Location
Marker shows the centre of Elko County; the queue data does not give exact sites.
Other requests in Elko County
- Solar + storage project 630, Elko CountySolar + storage Β· 53.0 MW Β· suspended
- Onshore wind project Company MZ, Elko CountyOnshore wind Β· 220 MW Β· withdrawn
- Onshore wind project Company GA, Elko CountyOnshore wind Β· 200 MW Β· withdrawn
- Geothermal project 263, Elko CountyGeothermal Β· 75.0 MW Β· withdrawn
- Geothermal project 255, Elko CountyGeothermal Β· 19.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem