Solar + storage project 630, Elko County is a 53.0 MW solar + storage request suspended in the West interconnection queue, in Elko County, Nevada, connecting to Idaho Power Company.
Queue statusPaused / redesign
- PlanningQueued Jan 2022 (current stage)
- ConsentedApr 2023 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 630
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Idaho Power Company
- Developer
- Elko County Solar 1, LLC
- Connection point (POI)
- Upper Salmon–Wells 138kV Line
- Location
- Elko County, Nevada
- Technology
- Solar: 53.0 MW · Battery
- Total requested
- 53.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Suspended
- Entered queue
- 10 January 2022
- Agreement signed
- 24 April 2023
- Proposed online date
- January 2025
Location
Marker shows the centre of Elko County; the queue data does not give exact sites.
Other requests in Elko County
- Solar + storage project Company PF, Elko CountySolar + storage · 460 MW · withdrawn
- Onshore wind project Company MZ, Elko CountyOnshore wind · 220 MW · withdrawn
- Onshore wind project Company GA, Elko CountyOnshore wind · 200 MW · withdrawn
- Geothermal project 263, Elko CountyGeothermal · 75.0 MW · withdrawn
- Geothermal project 255, Elko CountyGeothermal · 19.9 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem