United States βΊ Grid βΊ Interconnection queues βΊ Nevada
GEOTHERMAL Β· WESTGeothermal project 263, Elko County
Geothermal project 263, Elko County is a 75.0 MW geothermal request withdrawn in the West interconnection queue, in Elko County, Nevada, connecting to Idaho Power Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2008 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 263
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Idaho Power Company
- Connection point (POI)
- 345kV
- Location
- Elko County, Nevada
- Technology
- Geothermal: 75.0 MW
- Total requested
- 75.0 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 21 July 2008
- Proposed online date
- November 2010
Location
Marker shows the centre of Elko County; the queue data does not give exact sites.
Other requests in Elko County
- Solar + storage project 630, Elko CountySolar + storage Β· 53.0 MW Β· suspended
- Solar + storage project Company PF, Elko CountySolar + storage Β· 460 MW Β· withdrawn
- Onshore wind project Company MZ, Elko CountyOnshore wind Β· 220 MW Β· withdrawn
- Onshore wind project Company GA, Elko CountyOnshore wind Β· 200 MW Β· withdrawn
- Geothermal project 255, Elko CountyGeothermal Β· 19.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem