๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues โ€บ Nebraska

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Nebraska

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown25545.7 GW
Active in queue16.5 GW85 requests
Agreement signed5,103 MW29 requests
Withdrawn25545.7 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

255 requests ยท page 1 of 6
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-2018-18, Banner County
Onshore wind
1,000 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Coal project GEN-2007-011N02, Lancaster County
Coal
600 MWWithdrawn / abandoned Lancaster, NESPP Mar 2007
Onshore wind project GI-1405, Banner County
Onshore wind
600 MWWithdrawn / abandoned Banner, NEWest Jun 2014target 2016
Onshore wind project GEN-2021-007, Knox County
Onshore wind
600 MWWithdrawn / abandoned Knox, NESPP May 20212025
Solar project GEN-2018-045, Banner County
Solar
550 MWWithdrawn / abandoned Banner, NESPP May 20182021
Onshore wind project GI-2018-17, Banner County
Onshore wind
502 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-16, Banner County
Onshore wind
502 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Solar project GEN-2018-044, Antelope County
Solar
500 MWWithdrawn / abandoned Antelope, NESPP May 20182025
Onshore wind project GEN-2023-116, Keith County
Onshore wind
500 MWWithdrawn / abandoned Keith, NESPP Oct 2023target 2030
Solar project GEN-2019-007, Lancaster County
Solar
500 MWWithdrawn / abandoned Lancaster, NESPP Apr 2019target 2022
Onshore wind project GEN-2018-110, Nemaha County
Onshore wind
500 MWWithdrawn / abandoned Nemaha, NESPP Nov 2018target 2023
Onshore wind project GEN-2016-159, Stanton County
Onshore wind
428 MWWithdrawn / abandoned Stanton, NESPP Nov 2016target 2020
Gas project GEN-2020-024, Sarpy County
Gas
425 MWWithdrawn / abandoned Sarpy, NESPP Apr 20202023
Gas project GEN-2020-035, Cass County
Gas
425 MWWithdrawn / abandoned Cass, NESPP Apr 20202023
Onshore wind project GEN-2019-029, Keith County
Onshore wind
404 MWWithdrawn / abandoned Keith, NESPP Apr 20192024
Onshore wind project GI-2018-10, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-7, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-12, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-8, Banner County
Onshore wind
401 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Coal project GEN-2007-011N01, Lancaster County
Coal
400 MWWithdrawn / abandoned Lancaster, NESPP Mar 2007
Coal project GEN-2001-039N, Hall County
Coal
400 MWWithdrawn / abandoned Hall, NESPP Nov 2001
Solar project GEN-2018-066, Lancaster County
Solar
400 MWWithdrawn / abandoned Lancaster, NESPP Oct 2018target 2022
Onshore wind project GEN-2008-121N01, Saline County
Onshore wind
400 MWWithdrawn / abandoned Saline, NESPP Oct 2008
Coal project GEN-2001-040N, Dawson County
Coal
400 MWWithdrawn / abandoned Dawson, NESPP Jan 2002
Onshore wind project GEN-2018-119, Johnson County
Onshore wind
400 MWWithdrawn / abandoned Johnson, NESPP Nov 2018target 2023
Onshore wind project GEN-2018-046, Banner County
Onshore wind
400 MWWithdrawn / abandoned Banner, NESPP May 20182025
Solar project GEN-2019-028, Lincoln County
Solar
400 MWWithdrawn / abandoned Lincoln, NESPP Apr 20192025
Onshore wind project GEN-2016-106, Keith County
Onshore wind
400 MWWithdrawn / abandoned Keith, NESPP Nov 20162020
Onshore wind project GI-2018-14, Banner County
Onshore wind
350 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Onshore wind project GI-2018-13, Banner County
Onshore wind
350 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Gas project GEN-2007-030N, Buffalo County
Gas
350 MWWithdrawn / abandoned Buffalo, NESPP Jul 2007
Onshore wind project GEN-2016-116, Dixon County
Onshore wind
320 MWWithdrawn / abandoned Dixon, NESPP Nov 2016target 2019
Onshore wind project GEN-2015-042, Dixon County
Onshore wind
320 MWWithdrawn / abandoned Dixon, NESPP Oct 2015target 2017
Solar project GEN-2017-212, Cedar County
Solar
310 MWWithdrawn / abandoned Cedar, NESPP Nov 2017target 2021
Solar project GEN-2017-008, Nuckolls County
Solar
305 MWWithdrawn / abandoned Nuckolls, NESPP Apr 2017target 2019
Solar project GEN-2022-175, Clay County
Solar
305 MWWithdrawn / abandoned Clay, NESPP Feb 2023target 2026
Solar + storage project GEN-2020-036, Cass County
Solar + storage
303 MWWithdrawn / abandoned Cass, NESPP Apr 20202023
Gas project GEN-2020-040, Cass County
Gas
303 MWWithdrawn / abandoned Cass, NESPP Apr 20202023
Onshore wind project GEN-2018-068, Madison County
Onshore wind
302 MWWithdrawn / abandoned Madison, NESPP Oct 2018target 2027
Onshore wind project GEN-2018-017, Keith County
Onshore wind
302 MWWithdrawn / abandoned Keith, NESPP Apr 2018target 2020
Onshore wind project GEN-2022-200, Holt County
Onshore wind
300 MWWithdrawn / abandoned Holt, NESPP Feb 2023target 2027
Onshore wind project GEN-2021-058, Madison County
Onshore wind
300 MWWithdrawn / abandoned Madison, NESPP Apr 2021target 2026
Onshore wind project GEN-2021-044, Dundy County
Onshore wind
300 MWWithdrawn / abandoned Dundy, NESPP Apr 2021target 2026
Onshore wind project GEN-2018-042, Johnson County
Onshore wind
300 MWWithdrawn / abandoned Johnson, NESPP May 20182025
Onshore wind project GEN-2023-117, Keith County
Onshore wind
300 MWWithdrawn / abandoned Keith, NESPP Oct 2023target 2030
Solar project GEN-2022-198, Lancaster County
Solar
300 MWWithdrawn / abandoned Lancaster, NESPP Feb 2023target 2028
Solar project GEN-2024-349, Hall County
Solar
300 MWWithdrawn / abandoned Hall, NESPP Mar 2025target 2029
Onshore wind project GEN-2021-060, Lancaster County
Onshore wind
300 MWWithdrawn / abandoned Lancaster, NESPP Apr 2021target 2027
Onshore wind project GEN-2024-151, Cheyenne County
Onshore wind
300 MWWithdrawn / abandoned Cheyenne, NESPP Mar 2025target 2030
Onshore wind project GI-2018-15, Banner County
Onshore wind
300 MWWithdrawn / abandoned Banner, NEWest Mar 2018target 2021
Page 1 of 6

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)