United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Minnesota (2018 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project J1106, Redwood County Onshore wind |
414 MW | Withdrawn / abandoned |
| Onshore wind project J1081, Polk County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project J977, Jackson County Onshore wind |
300 MW | Withdrawn / abandoned |
| Solar project J1179, Chisago County Solar |
300 MW | Withdrawn / abandoned |
| Solar project J1061, Wabasha County Solar |
300 MW | Withdrawn / abandoned |
| Onshore wind project J971, Nobles County Onshore wind |
250 MW | Withdrawn / abandoned |
| Solar project J1149, Yellow Medicine County Solar |
200 MW | Withdrawn / abandoned |
| Solar project J1105, Dakota County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project J965, Cottonwood County Onshore wind |
150 MW | Withdrawn / abandoned |
| Solar project J1128, Freeborn County Solar |
150 MW | Withdrawn / abandoned |
| Solar project J1108, Douglas County Solar |
150 MW | Withdrawn / abandoned |
| Solar project J1036, Cottonwood County Solar |
130 MW | Withdrawn / abandoned |
| Solar project J1057, Jackson County Solar |
125 MW | Withdrawn / abandoned |
| Solar project J1086, Nobles County Solar |
120 MW | Withdrawn / abandoned |
| Solar project J1143, Morrison County Solar |
100 MW | Withdrawn / abandoned |
| Onshore wind project J958, Lincoln County Onshore wind |
100 MW | Withdrawn / abandoned |
| Solar project J1110, Mower County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J1140, Benton County Solar |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project J951, Kittson County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Battery storage project J1032, Wabasha County Battery storage |
50.0 MW | Withdrawn / abandoned |
| Solar project J1008, Faribault County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project J1001, Lincoln County Solar |
40.0 MW | Withdrawn / abandoned |
| Solar project J1098, Jackson County Solar |
40.0 MW | Withdrawn / abandoned |
| Solar project J1038, Grant County Solar |
32.5 MW | Withdrawn / abandoned |
| Battery storage project J1054, Goodhue County Battery storage |
30.0 MW | Withdrawn / abandoned |
| Battery storage project J1041, Jackson County Battery storage |
20.0 MW | Withdrawn / abandoned |
| Battery storage project J1037, Murray County Battery storage |
15.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)