United States β€Ί Grid β€Ί Interconnection queues β€Ί Maryland

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Maryland (2018 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown23616 MW
Active in queue49.0 MW1 requests
Agreement signed0.0 MW0 requests
Withdrawn23616 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

23 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Offshore wind project AD2-212, Worcester County
Offshore wind
160 MWWithdrawn / abandoned Worcester, MDPJM Mar 2018target 2022
Gas project AD2-104, Baltimore County
Gas
145 MWWithdrawn / abandoned Baltimore, MDPJM Mar 2018target 2019
Other project AE1-077, Allegany County
Other
100 MWWithdrawn / abandoned Allegany, MDPJM Aug 2018target 2020
Solar project AD2-174, St. Mary's County
Solar
52.5 MWWithdrawn / abandoned St. Mary's, MDPJM Mar 2018target 2020
Richfield Solar and Storage
Battery storage
20.0 MWWithdrawn / abandoned Dorchester, MDPJM Aug 2018target 2024
Whitetail VI
Solar
20.0 MWWithdrawn / abandoned St. Mary's, MDPJM Nov 2018target 2023
Solar + storage project AE1-231, Charles County
Solar + storage
20.0 MWWithdrawn / abandoned Charles, MDPJM Sep 2018target 2020
Battery storage project AD2-095, Dorchester County
Battery storage
20.0 MWWithdrawn / abandoned Dorchester, MDPJM Mar 2018target 2021
Solar project AD2-045, Queen Anne's County
Solar
20.0 MWWithdrawn / abandoned Queen Anne's, MDPJM Jan 2018target 2019
Solar project AE2-030, Allegany County
Solar
18.0 MWWithdrawn / abandoned Allegany, MDPJM Dec 2018target 2020
Other project AD2-103, Baltimore County
Other
14.0 MWWithdrawn / abandoned Baltimore, MDPJM Mar 2018target 2019
Gas project AE1-151, Baltimore City County
Gas
9.0 MWWithdrawn / abandoned Baltimore City, MDPJM Sep 2018target 2020
Solar project AE2-002, Prince George's County
Solar
3.6 MWWithdrawn / abandoned Prince George's, MDPJM Oct 2018target 2019
Solar project AE2-003, Prince George's County
Solar
3.0 MWWithdrawn / abandoned Prince George's, MDPJM Oct 2018target 2019
Spectrum Solar II
Solar
3.0 MWWithdrawn / abandoned Prince George's, MDPJM Mar 2018target 2022
Solar project AE1-011
Solar
1.5 MWWithdrawn / abandoned MDPJM May 2018target 2019
5203 Saint Barnabas Road
Solar
1.4 MWWithdrawn / abandoned Prince George's, MDPJM May 2018target 2022
Solar project AE1-082, Charles County
Solar
1.3 MWWithdrawn / abandoned Charles, MDPJM Aug 2018target 2018
Solar project AE1-016, Prince George's County
Solar
1.1 MWWithdrawn / abandoned Prince George's, MDPJM May 2018target 2019
Battery storage project AE1-048, Queen Anne's County
Battery storage
1.0 MWWithdrawn / abandoned Queen Anne's, MDPJM Jul 2018
4179 Suitland Road
Solar
0.9 MWWithdrawn / abandoned Prince George's, MDPJM May 2018target 2022
Solar project AE1-014, Prince George's County
Solar
0.5 MWWithdrawn / abandoned Prince George's, MDPJM May 2018target 2019
1724 64th Street
Solar
0.5 MWWithdrawn / abandoned Prince George's, MDPJM Oct 2018target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)