Solar project AE1-082, Charles County

Solar project AE1-082, Charles County is a 1.3 MW solar request withdrawn in the PJM interconnection queue, in Charles County, Maryland, connecting to SMECO.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2018 (completed)
  2. Withdrawn / abandonedSep 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AE1-082
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
SMECO
Connection point (POI)
Charles County 13 kV
Location
Charles County, Maryland
Technology
Solar: 1.3 MW
Total requested
1.3 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
28 August 2018
Proposed online date
November 2018
Withdrawn
September 2018

Location

Marker shows the centre of Charles County; the queue data does not give exact sites.