United States βΊ Grid βΊ Interconnection queues βΊ Maryland
SOLAR Β· PJMSolar project AE1-011
Solar project AE1-011 is a 1.5 MW solar request withdrawn in the PJM interconnection queue, connecting to PEPCO.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2018 (completed)
- Withdrawn / abandonedSep 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AE1-011
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PEPCO
- Connection point (POI)
- Livingston Road 13 kV
- Location
- Maryland
- Technology
- Solar: 1.5 MW
- Total requested
- 1.5 MW
- Service type
- Energy only (ERIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 2 May 2018
- Proposed online date
- March 2019
- Withdrawn
- September 2018
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem