United States β€Ί Grid β€Ί Interconnection queues β€Ί Louisiana

OCTARY USA Β· INTERCONNECTION QUEUES

Queue projects under construction in Louisiana

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown151,639 MW
Active in queue37.6 GW140 requests
Agreement signed3,056 MW18 requests
Withdrawn31059.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

15 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1421, East Feliciana Parish County
Solar
300 MWUnder construction East Feliciana Parish, LAMISO Apr 2019target 2024
Solar project J1076, St. James Parish County
Solar
200 MWUnder construction St. James Parish, LAMISO Mar 2018target 2022
Solar project J1424, Beauregard Parish County
Solar
200 MWUnder construction Beauregard Parish, LAMISO Apr 2019target 2024
Solar project J1286, Evangeline Parish County
Solar
150 MWUnder construction Evangeline Parish, LAMISO Apr 2019target 2025
Solar project J1644, St. Landry Parish County
Solar
150 MWUnder construction St. Landry Parish, LAMISO Jun 2020target 2024
Solar project J909, Tangipahoa Parish County
Solar
100 MWUnder construction Tangipahoa Parish, LAMISO Jun 2017target 2022
Solar project J1239, Ouachita Parish County
Solar
100 MWUnder construction Ouachita Parish, LAMISO Apr 2019target 2024
Solar project J1219, Tangipahoa Parish County
Solar
100 MWUnder construction Tangipahoa Parish, LAMISO Apr 2019target 2024
Solar project J1367, St. Mary Parish County
Solar
95.0 MWUnder construction St. Mary Parish, LAMISO Apr 2019target 2022
Solar project J1158, St. James Parish County
Solar
70.0 MWUnder construction St. James Parish, LAMISO Mar 2018target 2022
Solar project J1361, Washington Parish County
Solar
50.0 MWUnder construction Washington Parish, LAMISO Apr 20192024
Solar project J1184, Washington Parish County
Solar
50.0 MWUnder construction Washington Parish, LAMISO Mar 20182021
Other project J868, Concordia Parish County
Other
37.2 MWUnder construction Concordia Parish, LAMISO Jun 2017target 1990
Battery storage project J1257, Tangipahoa Parish County
Battery storage
20.0 MWUnder construction Tangipahoa Parish, LAMISO Apr 2019target 2024
Other project J1247, St. Mary Parish County
Other
17.0 MWUnder construction St. Mary Parish, LAMISO Apr 20192023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)