United States βΊ Grid βΊ Interconnection queues βΊ Kansas
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in Kansas (2023 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project GEN-2022-161, Butler County Onshore wind |
360 MW | In study |
| Solar project GEN-2023-015, Finney County Solar |
330 MW | In study |
| Solar project GEN-2023-099, Jackson County Solar |
300 MW | In study |
| Onshore wind project GEN-2023-107, Finney County Onshore wind |
300 MW | In study |
| Solar project GEN-2023-220, Osage County Solar |
250 MW | In study |
| Solar project GEN-2023-221, Osage County Solar |
250 MW | In study |
| Solar project GEN-2022-214, Sumner County Solar |
239 MW | In study |
| Battery storage project GEN-2023-037, Wyandotte County Battery storage |
200 MW | In study |
| Onshore wind project GEN-2023-172, Kearny County Onshore wind |
200 MW | In study |
| Solar project GEN-2023-SR28, Ford County Solar |
150 MW | Agreement signed |
| Solar project GEN-2023-034, Sedgwick County Solar |
130 MW | In study |
| Onshore wind project GEN-2023-173, Kearny County Onshore wind |
100 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)