United States βΊ Grid βΊ Interconnection queues βΊ Iowa
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in Iowa (2016 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project J578, Audubon County Onshore wind |
400 MW | Withdrawn / abandoned |
| Onshore wind project J610, Benton County Onshore wind |
300 MW | Withdrawn / abandoned |
| Onshore wind project J731, Palo Alto County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J733, Franklin County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J691, Boone County Onshore wind |
160 MW | Withdrawn / abandoned |
| Onshore wind project J563, Marshall County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J562, Marshall County Onshore wind |
120 MW | Withdrawn / abandoned |
| Onshore wind project J776, Franklin County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project J777, Franklin County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project J615, Black Hawk County Onshore wind |
70.0 MW | Withdrawn / abandoned |
| Onshore wind project J767, Hancock County Onshore wind |
12.0 MW | Withdrawn / abandoned |
| Onshore wind project J764, Story County Onshore wind |
12.0 MW | Withdrawn / abandoned |
| Onshore wind project J768, Story County Onshore wind |
12.0 MW | Withdrawn / abandoned |
| Onshore wind project J772, Cerro Gordo County Onshore wind |
7.4 MW | Withdrawn / abandoned |
| Onshore wind project J763, Hancock County Onshore wind |
5.3 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)