ONSHORE WIND Β· MISO

Onshore wind project J772, Cerro Gordo County

Onshore wind project J772, Cerro Gordo County is a 7.4 MW onshore wind request withdrawn in the MISO interconnection queue, in Cerro Gordo County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2016 (completed)
  2. Withdrawn / abandonedJul 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J772
Grid region
MISO (Midcontinent)
Connection point (POI)
Unknown
Location
Cerro Gordo County, Iowa
Technology
Wind: 7.4 MW
Total requested
7.4 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
14 November 2016
Proposed online date
January 2018
Withdrawn
July 2017

Location

Marker shows the centre of Cerro Gordo County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Cerro Gordo County