United States โบ Grid โบ Interconnection queues โบ Illinois
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in Illinois (2021 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Wind + storage project J2039, Sangamon County Wind + storage |
400 MW | Withdrawn / abandoned |
| Solar project AH1-601, Lee County Solar |
300 MW | Withdrawn / abandoned |
| Onshore wind project AG2-197, Lee County Onshore wind |
296 MW | Withdrawn / abandoned |
| Solar project AH1-633, Livingston County Solar |
288 MW | Withdrawn / abandoned |
| Battery storage project AG2-357, Will County Battery storage ยท Bluegill Energy Storage LLC |
250 MW | Withdrawn / abandoned |
| Battery storage project AH1-559, Will County Battery storage |
250 MW | Withdrawn / abandoned |
| Battery storage project AH1-602, Lee County Battery storage |
225 MW | Withdrawn / abandoned |
| Onshore wind project AG2-674, Whiteside County Onshore wind |
212 MW | Withdrawn / abandoned |
| Battery storage project J2204, St. Clair County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project AH1-148, Ogle County Solar ยท Mound Solar, LLC |
200 MW | Withdrawn / abandoned |
| Onshore wind project AG2-527, Stark County Onshore wind ยท Invenergy Wind Development LLC |
200 MW | Withdrawn / abandoned |
| Onshore wind project AH1-297, Stark County Onshore wind ยท Invenergy Wind Development LLC |
200 MW | Withdrawn / abandoned |
| Solar project AH1-232, Winnebago County Solar |
175 MW | Withdrawn / abandoned |
| Solar + storage project AH1-540, Ogle County Solar + storage ยท Golden Harvest Energy, LLC |
165 MW | Withdrawn / abandoned |
| Solar project J2306, Perry County Solar |
150 MW | Withdrawn / abandoned |
| Battery storage project AH1-560, Will County Battery storage ยท University Park Energy, LLC |
150 MW | Withdrawn / abandoned |
| Solar project AH1-599, Lee County Solar |
150 MW | Withdrawn / abandoned |
| Battery storage project AH1-616, Cook County Battery storage |
150 MW | Withdrawn / abandoned |
| Onshore wind project AH1-003, Lasalle County Onshore wind |
130 MW | Withdrawn / abandoned |
| Onshore wind project AH1-295, Mclean County Onshore wind ยท Invenergy Wind Development LLC |
130 MW | Withdrawn / abandoned |
| Solar + storage project AG2-517, Rock Island County Solar + storage |
120 MW | Withdrawn / abandoned |
| Solar project J1652, Champaign County Solar |
116 MW | Withdrawn / abandoned |
| Solar project AG2-467, Logan County Solar ยท Invenergy Solar Project Development LLC |
115 MW | Withdrawn / abandoned |
| Battery storage project AH1-600, Lee County Battery storage |
110 MW | Withdrawn / abandoned |
| Other project J2196, Montgomery County Other |
100 MW | Withdrawn / abandoned |
| Solar project AH1-657, Dekalb County Solar |
100 MW | Withdrawn / abandoned |
| Solar project J2125, Clay County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AH1-659, Lee County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AH1-294, Mclean County Solar ยท Blooming Grove Solar Energy Center LLC |
100 MW | Withdrawn / abandoned |
| Solar project AH1-654, Christian County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AH1-199, Livingston County Solar |
100 MW | Withdrawn / abandoned |
| Onshore wind project J2115, Macon County Onshore wind |
98.3 MW | Withdrawn / abandoned |
| Solar project AH1-009, Dekalb County Solar |
86.0 MW | Withdrawn / abandoned |
| Battery storage project AH1-190, Lake County Battery storage |
80.0 MW | Withdrawn / abandoned |
| Solar project AH1-544, Lasalle County Solar |
67.7 MW | Withdrawn / abandoned |
| Battery storage project AH1-296, Logan County Battery storage ยท Invenergy Solar Project Development LLC |
60.0 MW | Withdrawn / abandoned |
| Battery storage project AH1-101, Cook County Battery storage |
57.8 MW | Withdrawn / abandoned |
| Battery storage project AH1-663, Cook County Battery storage |
57.8 MW | Withdrawn / abandoned |
| Solar project J2158, Clark County Solar |
50.0 MW | Withdrawn / abandoned |
| Battery storage project J2161, Fulton County Battery storage |
50.0 MW | Withdrawn / abandoned |
| Battery storage project J1655, Jefferson County Battery storage |
50.0 MW | Withdrawn / abandoned |
| Battery storage project AH1-361, Woodford County Battery storage ยท Minonk Solar, LLC |
50.0 MW | Withdrawn / abandoned |
| Battery storage project AH1-354, Stephenson County Battery storage ยท Blue Violet Energy, LLC |
40.0 MW | Withdrawn / abandoned |
| Solar project AH1-045, Lake County Solar ยท Zion Energy LLC |
23.0 MW | Withdrawn / abandoned |
| Solar + storage project AH1-191, Tazewell County Solar + storage |
20.9 MW | Withdrawn / abandoned |
| Solar project AG2-147, Livingston County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AH1-353, Stephenson County Solar ยท Blue Violet Energy, LLC |
20.0 MW | Withdrawn / abandoned |
| Solar project AH1-029, Cook County Solar |
1.0 MW | Withdrawn / abandoned |
| Solar project AH1-030, Cook County Solar |
1.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)