United States โ€บ Grid โ€บ Interconnection queues โ€บ Illinois

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in Illinois (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown496,216 MW
Active in queue1,426 MW10 requests
Agreement signed0.0 MW0 requests
Withdrawn496,216 MW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

49 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Wind + storage project J2039, Sangamon County
Wind + storage
400 MWWithdrawn / abandoned Sangamon, ILMISO Aug 2021target 2024
Solar project AH1-601, Lee County
Solar
300 MWWithdrawn / abandoned Lee, ILPJM Sep 2021target 2025
Onshore wind project AG2-197, Lee County
Onshore wind
296 MWWithdrawn / abandoned Lee, ILPJM Feb 2021target 2024
Solar project AH1-633, Livingston County
Solar
288 MWWithdrawn / abandoned Livingston, ILPJM Sep 2021target 2024
Battery storage project AG2-357, Will County
Battery storage ยท Bluegill Energy Storage LLC
250 MWWithdrawn / abandoned Will, ILPJM Mar 2021target 2024
Battery storage project AH1-559, Will County
Battery storage
250 MWWithdrawn / abandoned Will, ILPJM Sep 2021target 2025
Battery storage project AH1-602, Lee County
Battery storage
225 MWWithdrawn / abandoned Lee, ILPJM Sep 2021target 2025
Onshore wind project AG2-674, Whiteside County
Onshore wind
212 MWWithdrawn / abandoned Whiteside, ILPJM Mar 2021target 2023
Battery storage project J2204, St. Clair County
Battery storage
200 MWWithdrawn / abandoned St. Clair, ILMISO Oct 2021target 2024
Solar project AH1-148, Ogle County
Solar ยท Mound Solar, LLC
200 MWWithdrawn / abandoned Ogle, ILPJM Aug 2021target 2025
Onshore wind project AG2-527, Stark County
Onshore wind ยท Invenergy Wind Development LLC
200 MWWithdrawn / abandoned Stark, ILPJM Mar 2021target 2025
Onshore wind project AH1-297, Stark County
Onshore wind ยท Invenergy Wind Development LLC
200 MWWithdrawn / abandoned Stark, ILPJM Sep 2021target 2025
Solar project AH1-232, Winnebago County
Solar
175 MWWithdrawn / abandoned Winnebago, ILPJM Sep 2021target 2025
Solar + storage project AH1-540, Ogle County
Solar + storage ยท Golden Harvest Energy, LLC
165 MWWithdrawn / abandoned Ogle, ILPJM Sep 2021target 2025
Solar project J2306, Perry County
Solar
150 MWWithdrawn / abandoned Perry, ILMISO Jul 2021target 2024
Battery storage project AH1-560, Will County
Battery storage ยท University Park Energy, LLC
150 MWWithdrawn / abandoned Will, ILPJM Sep 2021target 2025
Solar project AH1-599, Lee County
Solar
150 MWWithdrawn / abandoned Lee, ILPJM Sep 2021target 2025
Battery storage project AH1-616, Cook County
Battery storage
150 MWWithdrawn / abandoned Cook, ILPJM Sep 2021target 2025
Onshore wind project AH1-003, Lasalle County
Onshore wind
130 MWWithdrawn / abandoned Lasalle, ILPJM Apr 2021target 2024
Onshore wind project AH1-295, Mclean County
Onshore wind ยท Invenergy Wind Development LLC
130 MWWithdrawn / abandoned Mclean, ILPJM Sep 2021target 2025
Solar + storage project AG2-517, Rock Island County
Solar + storage
120 MWWithdrawn / abandoned Rock Island, ILPJM Mar 2021target 2023
Solar project J1652, Champaign County
Solar
116 MWWithdrawn / abandoned Champaign, ILMISO Dec 2021target 2023
Solar project AG2-467, Logan County
Solar ยท Invenergy Solar Project Development LLC
115 MWWithdrawn / abandoned Logan, ILPJM Mar 2021target 2025
Battery storage project AH1-600, Lee County
Battery storage
110 MWWithdrawn / abandoned Lee, ILPJM Sep 2021target 2025
Other project J2196, Montgomery County
Other
100 MWWithdrawn / abandoned Montgomery, ILMISO Aug 2021target 2028
Solar project AH1-657, Dekalb County
Solar
100 MWWithdrawn / abandoned Dekalb, ILPJM Sep 2021target 2024
Solar project J2125, Clay County
Solar
100 MWWithdrawn / abandoned Clay, ILMISO Aug 2021target 2024
Solar project AH1-659, Lee County
Solar
100 MWWithdrawn / abandoned Lee, ILPJM Sep 2021target 2024
Solar project AH1-294, Mclean County
Solar ยท Blooming Grove Solar Energy Center LLC
100 MWWithdrawn / abandoned Mclean, ILPJM Sep 2021target 2025
Solar project AH1-654, Christian County
Solar
100 MWWithdrawn / abandoned Christian, ILPJM Sep 2021target 2024
Solar project AH1-199, Livingston County
Solar
100 MWWithdrawn / abandoned Livingston, ILPJM Sep 2021target 2025
Onshore wind project J2115, Macon County
Onshore wind
98.3 MWWithdrawn / abandoned Macon, ILMISO Aug 2021target 2024
Solar project AH1-009, Dekalb County
Solar
86.0 MWWithdrawn / abandoned Dekalb, ILPJM Apr 2021target 2024
Battery storage project AH1-190, Lake County
Battery storage
80.0 MWWithdrawn / abandoned Lake, ILPJM Sep 2021target 2025
Solar project AH1-544, Lasalle County
Solar
67.7 MWWithdrawn / abandoned Lasalle, ILPJM Sep 2021target 2025
Battery storage project AH1-296, Logan County
Battery storage ยท Invenergy Solar Project Development LLC
60.0 MWWithdrawn / abandoned Logan, ILPJM Sep 2021target 2025
Battery storage project AH1-101, Cook County
Battery storage
57.8 MWWithdrawn / abandoned Cook, ILPJM Jul 2021target 2024
Battery storage project AH1-663, Cook County
Battery storage
57.8 MWWithdrawn / abandoned Cook, ILPJM Sep 2021target 2024
Solar project J2158, Clark County
Solar
50.0 MWWithdrawn / abandoned Clark, ILMISO Aug 2021target 2024
Battery storage project J2161, Fulton County
Battery storage
50.0 MWWithdrawn / abandoned Fulton, ILMISO Aug 2021target 2024
Battery storage project J1655, Jefferson County
Battery storage
50.0 MWWithdrawn / abandoned Jefferson, ILMISO Dec 2021target 2022
Battery storage project AH1-361, Woodford County
Battery storage ยท Minonk Solar, LLC
50.0 MWWithdrawn / abandoned Woodford, ILPJM Sep 2021target 2024
Battery storage project AH1-354, Stephenson County
Battery storage ยท Blue Violet Energy, LLC
40.0 MWWithdrawn / abandoned Stephenson, ILPJM Sep 2021target 2024
Solar project AH1-045, Lake County
Solar ยท Zion Energy LLC
23.0 MWWithdrawn / abandoned Lake, ILPJM Jul 2021target 2023
Solar + storage project AH1-191, Tazewell County
Solar + storage
20.9 MWWithdrawn / abandoned Tazewell, ILPJM Sep 2021target 2025
Solar project AG2-147, Livingston County
Solar
20.0 MWWithdrawn / abandoned Livingston, ILPJM Feb 2021target 2024
Solar project AH1-353, Stephenson County
Solar ยท Blue Violet Energy, LLC
20.0 MWWithdrawn / abandoned Stephenson, ILPJM Sep 2021target 2024
Solar project AH1-029, Cook County
Solar
1.0 MWWithdrawn / abandoned Cook, ILPJM Jun 2021target 2021
Solar project AH1-030, Cook County
Solar
1.0 MWWithdrawn / abandoned Cook, ILPJM Jun 2021target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)