United States โ€บ Grid โ€บ Interconnection queues โ€บ Idaho

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in Idaho (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2410.2 GW
Active in queue10.2 GW24 requests
Agreement signed2,842 MW11 requests
Withdrawn5313.2 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project 660, Owyhee County
Solar + storage ยท Sawtooth DevCo, LLC
1,650 MWPaused / redesign Owyhee, IDWest Jun 2022target 2027
Solar + storage project 659, Jerome County
Solar + storage ยท Sawtooth DevCo, LLC
1,650 MWPaused / redesign Jerome, IDWest Jun 2022target 2027
Solar + storage project 662, Power County
Solar + storage ยท Sawtooth DevCo, LLC
1,000 MWPaused / redesign Power, IDWest Jun 2022target 2027
Other project 635, Gooding County
Other ยท Taurus Wind LLC
1,000 MWPaused / redesign Gooding, IDWest Feb 2022target 2029
Solar + storage project C2-45, Power County
Solar + storage ยท NextEra Energy Resources Interconnection Holdings, LLC
600 MWAgreement signed Power, IDWest Apr 2022target 2030
Solar + storage project 667, Elmore County
Solar + storage ยท Martha Fields Energy Center, LLC
400 MWPaused / redesign Elmore, IDWest Aug 2022target 2029
Solar + storage project 665, Ada County
Solar + storage ยท Blacks Creek Energy Center, LLC
400 MWAgreement signed Ada, IDWest Aug 2022target 2027
Battery storage project 696, Owyhee County
Battery storage ยท KCE ID 1, LLC
330 MWAgreement signed Owyhee, IDWest Dec 2022target 2026
Solar + storage project 655, Bear Lake County
Solar + storage ยท Aurora Solar LLC
325 MWPaused / redesign Bear Lake, IDWest May 2022target 2026
Battery storage project 632, Owyhee County
Battery storage ยท NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Owyhee, IDWest Jan 2022target 2025
Solar + storage project 656, Jerome County
Solar + storage ยท Red Bridge Energy, LLC
300 MWPaused / redesign Jerome, IDWest May 2022target 2027
Solar + storage project C2-82, Bannock County
Solar + storage ยท BRP Garnet 1, LLC
300 MWAgreement signed Bannock, IDWest May 2022target 2027
Onshore wind project C2-92, Bingham County
Onshore wind ยท PacifiCorp
206 MWIn study Bingham, IDWest May 2022target 2026
Solar + storage project 669, Ada County
Solar + storage ยท Bluebird Solar Project, LLC
200 MWAgreement signed Ada, IDWest Aug 2022target 2028
Battery storage project 641, Power County
Battery storage ยท Fresh Air Energy II, LLC
200 MWPaused / redesign Power, IDWest Feb 2022target 2026
Solar + storage project 666, Canyon County
Solar + storage ยท Powers Butte Energy Center, LLC
200 MWPaused / redesign Canyon, IDWest Aug 2022target 2026
Battery storage project 633, Jerome County
Battery storage ยท NextEra Energy Resources Interconnection Holdings, LLC
200 MWAgreement signed Jerome, IDWest Jan 2022target 2027
Solar + storage project C2-54, Lincoln County
Solar + storage ยท Star Lake Solar, LLC
200 MWAgreement signed Lincoln, IDWest May 2022target 2036
Onshore wind project C2-91, Bonneville County
Onshore wind ยท PacifiCorp
153 MWIn study Bonneville, IDWest May 2022target 2026
Battery storage project 639, Ada County
Battery storage ยท Idaho Power Companyโ€šร„รฎPower Supply
150 MWAgreement signed Ada, IDWest Feb 2022target 2026
Battery storage project 640, Ada County
Battery storage ยท Idaho Power Companyโ€šร„รฎPower Supply
150 MWPaused / redesign Ada, IDWest Feb 2022target 2026
Solar project 636, Elmore County
Solar ยท Soles Rest Solar LLC
149 MWAgreement signed Elmore, IDWest Feb 2022target 2028
Solar + storage project 654, Bingham County
Solar + storage ยท Pingree Solar LLC
130 MWPaused / redesign Bingham, IDWest May 2022target 2028
Battery storage project 634, Owyhee County
Battery storage ยท Idaho Power Companyโ€šร„รฎPower Supply
13.0 MWAgreement signed Owyhee, IDWest Jan 2022target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)