Withdrawn queue requests in Georgia (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown304,442 MW
Active in queue2,085 MW12 requests
Agreement signed920 MW4 requests
Withdrawn304,442 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

30 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-794, Turner County
Solar
343 MWWithdrawn / abandoned Turner, GASoutheast May 2019
Solar project IC-773, Burke County
Solar
280 MWWithdrawn / abandoned Burke, GASoutheast Feb 2019
Solar project IC-823, Floyd County
Solar
225 MWWithdrawn / abandoned Floyd, GASoutheast Oct 2019target 2022
Solar project IC-824, Floyd County
Solar
225 MWWithdrawn / abandoned Floyd, GASoutheast Oct 2019
Solar + storage project IC-842, Brantley County
Solar + storage
211 MWWithdrawn / abandoned Brantley, GASoutheast Dec 2019
Solar + storage project IC-792, Terrell County
Solar + storage
200 MWWithdrawn / abandoned Terrell, GASoutheast May 2019
Battery storage project IC-827, Bartow County
Battery storage
200 MWWithdrawn / abandoned Bartow, GASoutheast Oct 2019
Battery storage project IC-821, Clayton County
Battery storage
200 MWWithdrawn / abandoned Clayton, GASoutheast Oct 2019target 2022
Solar + storage project IC-833, Decatur County
Solar + storage
200 MWWithdrawn / abandoned Decatur, GASoutheast Oct 2019
Battery storage project IC-830, Fulton County
Battery storage
200 MWWithdrawn / abandoned Fulton, GASoutheast Oct 2019
Battery storage project IC-819, Douglas County
Battery storage
200 MWWithdrawn / abandoned Douglas, GASoutheast Oct 2019target 2022
Solar + storage project IC-843, Ware County
Solar + storage
163 MWWithdrawn / abandoned Ware, GASoutheast Dec 2019target 2022
Solar project IC-779, Burke County
Solar
150 MWWithdrawn / abandoned Burke, GASoutheast Feb 2019
Solar project IC-798, Macon County
Solar
150 MWWithdrawn / abandoned Macon, GASoutheast Jul 2019target 2024
Solar project IC-799, Baldwin County
Solar
150 MWWithdrawn / abandoned Baldwin, GASoutheast Jul 2019target 2022
Solar project IC-807, Pike County
Solar
145 MWWithdrawn / abandoned Pike, GASoutheast Sep 2019
Solar project IC-776, Emanuel County
Solar
125 MWWithdrawn / abandoned Emanuel, GASoutheast Feb 2019
Solar + storage project IC-836, Clay County
Solar + storage
120 MWWithdrawn / abandoned Clay, GASoutheast Oct 2019
Battery storage project IC-820, Douglas County
Battery storage
100 MWWithdrawn / abandoned Douglas, GASoutheast Oct 2019target 2022
Battery storage project IC-822, Clayton County
Battery storage
100 MWWithdrawn / abandoned Clayton, GASoutheast Oct 2019
Battery storage project IC-829, Fulton County
Battery storage
100 MWWithdrawn / abandoned Fulton, GASoutheast Oct 2019
Battery storage project IC-828, Bartow County
Battery storage
100 MWWithdrawn / abandoned Bartow, GASoutheast Oct 2019
Solar project IC-840, Decatur County
Solar
100 MWWithdrawn / abandoned Decatur, GASoutheast Dec 2019
Solar + storage project IC-802, Tattnall County
Solar + storage
85.0 MWWithdrawn / abandoned Tattnall, GASoutheast Aug 2019
Solar project IC-771, Warren County
Solar
80.0 MWWithdrawn / abandoned Warren, GASoutheast Jan 2019
Solar + storage project IC-835, Miller County
Solar + storage
80.0 MWWithdrawn / abandoned Miller, GASoutheast Oct 2019
Solar project IC-777, Bibb County
Solar
70.0 MWWithdrawn / abandoned Bibb, GASoutheast Feb 2019
Solar + storage project IC-834, Miller County
Solar + storage
70.0 MWWithdrawn / abandoned Miller, GASoutheast Oct 2019
Solar project IC-778, Dodge County
Solar
50.0 MWWithdrawn / abandoned Dodge, GASoutheast Feb 2019
Solar project IC-790, Baker County
Solar
19.3 MWWithdrawn / abandoned Baker, GASoutheast Apr 2019

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)