Solar + storage project IC-792, Terrell County

Solar + storage project IC-792, Terrell County is a 200 MW solar + storage request withdrawn in the Southeast interconnection queue, in Terrell County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2019 (completed)
  2. Withdrawn / abandonedOct 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-792
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Dawson Primary 115 kV Bus
Location
Terrell County, Georgia
Technology
Solar: 200 MW Β· Battery
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
10 May 2019
Withdrawn
October 2019

Location

Marker shows the centre of Terrell County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Terrell County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem