United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Colorado (2025 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4410.6 GW
Active in queue10.6 GW44 requests
Agreement signed0.0 MW0 requests
Withdrawn91,448 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

44 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project GI-2025-04, Kiowa County
Solar + storage
800 MWIn study Kiowa, COWest Apr 2025target 2032
Solar + storage project GI-2025-06, Arapahoe County
Solar + storage
750 MWIn study Arapahoe, COWest Apr 2025target 2029
Onshore wind project CSUT-2025-1, Lincoln County
Onshore wind
500 MWIn study Lincoln, COWest Mar 2025target 2027
Gas project CSUT-2025-7, El Paso County
Gas
412 MWIn study El Paso, COWest Mar 2025target 2028
Solar project GI-2025-09, Cheyenne County
Solar
400 MWIn study Cheyenne, COWest Apr 2025target 2029
Solar + storage project GI-2025-08, El Paso County
Solar + storage
400 MWIn study El Paso, COWest Apr 2025target 2029
Solar + storage project GI-2025-07, Morgan County
Solar + storage
360 MWIn study Morgan, COWest Apr 2025target 2029
Solar + storage project GI-2025-12, Adams County
Solar + storage
355 MWIn study Adams, COWest May 2025target 2029
Solar + storage project GI-2025-03, Kiowa County
Solar + storage
325 MWIn study Kiowa, COWest Apr 2025target 2031
Solar + storage project GI-CS-2025-21, Pueblo County
Solar + storage
325 MWIn study Pueblo, COWest Sep 2025target 2030
Solar project GI-CS-2025-05, Weld County
Solar
300 MWIn study Weld, COWest Sep 2025target 2029
Solar + storage project GI-2025-02, Cheyenne County
Solar + storage
300 MWIn study Cheyenne, COWest Apr 2025target 2030
Other project GI-CS-2025-29, Yuma County
Other
300 MWIn study Yuma, COWest Oct 2025target 2031
Solar + storage project GI-2025-01, Morgan County
Solar + storage
300 MWIn study Morgan, COWest Apr 2025target 2030
Solar + storage project GI-CS-2025-03, Kit Carson County
Solar + storage
300 MWIn study Kit Carson, COWest Sep 2025target 2028
Onshore wind project GI-CS-2025-24, Kit Carson County
Onshore wind
225 MWIn study Kit Carson, COWest Sep 2025target 2029
Battery storage project GI-SISS-2025-06, Logan County
Battery storage
200 MWIn study Logan, COWest Oct 2025target 2027
Battery storage project GI-RSC-2025-02, Moffat County
Battery storage
200 MWIn study Moffat, COWest Jul 2025target 2029
Solar + storage project GI-CS-2025-20, Morgan County
Solar + storage
200 MWIn study Morgan, COWest Sep 2025target 2029
Solar + storage project GI-CS-2025-19, Morgan County
Solar + storage
200 MWIn study Morgan, COWest Sep 2025target 2029
Solar + storage project GI-CS-2025-17, Moffat County
Solar + storage
200 MWIn study Moffat, COWest Sep 2025target 2029
Onshore wind project GI-CS-2025-07, Kit Carson County
Onshore wind
199 MWIn study Kit Carson, COWest Sep 2025target 2029
Solar + storage project GI-CS-2025-02, Adams County
Solar + storage
199 MWIn study Adams, COWest Sep 2025target 2031
Gas project GI-CS-2025-27, Delta County
Gas
199 MWIn study Delta, COWest Oct 2025target 2029
Onshore wind project GI-CS-2025-26, Kit Carson County
Onshore wind
199 MWIn study Kit Carson, COWest Oct 2025target 2029
Solar project GI-CS-2025-09, Alamosa County
Solar
199 MWIn study Alamosa, COWest Sep 2025target 2028
Onshore wind project GI-CS-2025-11, Lincoln County
Onshore wind
199 MWIn study Lincoln, COWest Sep 2025target 2028
Onshore wind project GI-CS-2025-08, Kit Carson County
Onshore wind
199 MWIn study Kit Carson, COWest Sep 2025target 2029
Onshore wind project GI-2025-10, Kit Carson County
Onshore wind
175 MWIn study Kit Carson, COWest Apr 2025target 2026
Solar + storage project GI-CS-2025-12, Las Animas County
Solar + storage
165 MWIn study Las Animas, COWest Sep 2025target 2029
Solar + storage project GI-CS-2025-16, Weld County
Solar + storage
150 MWIn study Weld, COWest Sep 2025target 2029
Solar + storage project GI-CS-2025-22, Huerfano County
Solar + storage
150 MWIn study Huerfano, COWest Sep 2025target 2030
Solar + storage project GI-CS-2025-23, Las Animas County
Solar + storage
150 MWIn study Las Animas, COWest Sep 2025target 2030
Battery storage project GI-SISS-2025-05, Kit Carson County
Battery storage
150 MWIn study Kit Carson, COWest Aug 2025target 2027
Solar project 25-011625, Weld County
Solar
143 MWIn study Weld, COWest Jan 2025target 2026
Solar + storage project GI-CS-2025-28, Prowers County
Solar + storage
110 MWIn study Prowers, COWest Oct 2025target 2030
Battery storage project CSUT-2025-6, El Paso County
Battery storage
100 MWIn study El Paso, COWest Mar 2025target 2027
Battery storage project CSUT-2025-8, El Paso County
Battery storage
100 MWIn study El Paso, COWest Mar 2025target 2028
Solar project CSUT-2025-2, El Paso County
Solar
100 MWIn study El Paso, COWest Mar 2025target 2028
Solar + storage project GI-CS-2025-10, Otero County
Solar + storage
100 MWIn study Otero, COWest Sep 2025target 2029
Battery storage project GI-SISS-2025-04, Kit Carson County
Battery storage
79.0 MWIn study Kit Carson, COWest Jul 2025target 2027
Onshore wind project GI-2025-05, Logan County
Onshore wind
75.0 MWIn study Logan, COWest May 2025target 2029
Solar project 25-041825, Larimer County
Solar
50.0 MWIn study Larimer, COWest Apr 2025target 2028
Battery storage project GI-RSC-2025-03, Montrose County
Battery storage
50.0 MWIn study Montrose, COWest Jul 2025target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)