United States βΊ Grid βΊ Interconnection queues βΊ California
OCTARY USA Β· INTERCONNECTION QUEUESInterconnection queue in California (2019 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar + storage project Q68, Los Angeles County Solar + storage |
2,400 MW | In study |
| Angeleno Solar Farm Solar + storage |
2,300 MW | Agreement signed |
| Sanborn Hybrid 3 Solar + storage |
2,159 MW | Agreement signed |
| Buttonbush Solar Hybrid Energy Center Solar + storage |
1,636 MW | Agreement signed |
| Oberon Solar + storage |
1,037 MW | Agreement signed |
| Bellefield 2 Solar Farm Solar + storage |
1,000 MW | Agreement signed |
| Pelicans Jaw Hybrid Solar Solar + storage |
1,000 MW | Agreement signed |
| Lycan Solar Solar + storage |
800 MW | Agreement signed |
| Calypso Solar Solar + storage |
800 MW | Agreement signed |
| Irving Storage Battery storage |
783 MW | Agreement signed |
| Kingsley Solar Farm Solar + storage |
720 MW | Agreement signed |
| Menifee Power Bank Battery storage |
680 MW | Agreement signed |
| Double Butte Storage Battery storage |
508 MW | Agreement signed |
| Goldback Solar Center Battery storage |
500 MW | Agreement signed |
| Aratina Solar Center 2 Solar + storage |
400 MW | Agreement signed |
| Jewelflower Storage Battery storage |
355 MW | Agreement signed |
| Humidor Storage 1 Battery storage |
305 MW | Agreement signed |
| Nighthawk Storage Battery storage |
300 MW | Agreement signed |
| Solar + storage project 2019-G1, Butte County Solar + storage |
300 MW | In study |
| Commerce Energy Storage Battery storage |
250 MW | Agreement signed |
| Cormorant Storage Battery storage |
250 MW | Agreement signed |
| Kingsroad Hybrid Solar Solar + storage |
204 MW | Agreement signed |
| Kestrel Storage Battery storage |
200 MW | Agreement signed |
| Sandpiper Storage Battery storage |
200 MW | Agreement signed |
| Tanager Storage Battery storage |
200 MW | Agreement signed |
| Avocet Storage Battery storage |
200 MW | Agreement signed |
| Lockhart Solar 2 Solar + storage |
165 MW | Agreement signed |
| Solar + storage project 2019-G42, San Bernardino County Solar + storage |
160 MW | In study |
| Sunrise Butte Solar + storage |
150 MW | Agreement signed |
| Noosa Energy Storage Battery storage |
99.0 MW | Agreement signed |
| Ventasso Energy Storage Battery storage |
50.8 MW | Agreement signed |
| Air Station 1 Solar + storage |
42.1 MW | In study |
| Dynamo Solar Solar |
24.5 MW | Agreement signed |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)