Completed queue projects in California (2011 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown15989 MW
Active in queue971 MW5 requests
Agreement signed971 MW5 requests
Withdrawn17523.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

15 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project Q19, Kern County
Solar
250 MWOperating Kern, CAWest Sep 20112016
Re Astoria
Solar
175 MWOperating Kern, CACAISO Mar 20112016
PV2 Panoche Valley Solar (Aka Sge Panoche Valley Solar)
Solar
140 MWOperating San Benito, CACAISO Mar 20112018
Solar project Q18, Kern County
Solar
100 MWOperating Kern, CAWest Sep 20112016
Blue Hornet Solar
Solar
100 MWOperating Imperial, CACAISO Mar 20112022
Lotus Solar Farm
Solar
50.0 MWOperating Madera, CACAISO Mar 20112020
Golden Hills 2 Wind
Onshore wind
36.0 MWOperating Alameda, CACAISO Mar 20112015
North Lancaster Solar (Fka Western Antelope DRY Ranch Addition)
Solar
20.0 MWOperating Los Angeles, CACAISO Mar 20112016
Kingbird Solar A (Fka Av Solar Ranch 2-A)
Solar
20.0 MWOperating Kern, CACAISO Mar 20112016
Burford Giffen
Solar
20.0 MWOperating Fresno, CACAISO Mar 20112017
Frontier Solar
Solar
20.0 MWOperating Kern, CACAISO Mar 20112019
Kingbird Solar B (Fka Av Solar Ranch 2-B
Solar
20.0 MWOperating Kern, CACAISO Mar 20112016
Columbia Solar Energy 2 Fka Columbia Solar Energy II
Solar
20.0 MWOperating Contra Costa, CACAISO Mar 20112015
Morelos Del Sol (Fka Twissleman I)
Solar
15.0 MWOperating Kern, CACAISO Mar 20112015
Vasco Wind Project
Onshore wind
3.1 MWOperating Contra Costa, CACAISO Mar 20112011

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)