United States › Grid › Interconnection queues › California

SOLAR · CAISO

North Lancaster Solar (Fka Western Antelope DRY Ranch Addition)

North Lancaster Solar (Fka Western Antelope DRY Ranch Addition) is a 20.0 MW solar request built and operating in the CAISO interconnection queue, in Los Angeles County, California, connecting to SCE.

Queue statusOperating
  1. PlanningQueued Mar 2011 (completed)
  2. ConsentedMar 2016 (completed)
  3. Construction (completed)
  4. OperatingDec 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
778
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Antelope Substation 66 kV bus
Location
Los Angeles County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Operational
Entered queue
31 March 2011
Agreement signed
9 March 2016
Proposed online date
December 2013
Came online
December 2016

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Los Angeles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem