United States › Grid › Interconnection queues › California

SOLAR · CAISO

Kingbird Solar A (Fka Av Solar Ranch 2-A)

Kingbird Solar A (Fka Av Solar Ranch 2-A) is a 20.0 MW solar request built and operating in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusOperating
  1. PlanningQueued Mar 2011 (completed)
  2. ConsentedMar 2014 (completed)
  3. Construction (completed)
  4. OperatingApr 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
795
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Whirlwind Substation 230 kV bus
Location
Kern County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
31 March 2011
Agreement signed
11 March 2014
Proposed online date
August 2013
Came online
April 2016

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem