United States › Grid › Interconnection queues › California

ONSHORE WIND · CAISO

Golden Hills 2 Wind

Golden Hills 2 Wind is a 36.0 MW onshore wind request built and operating in the CAISO interconnection queue, in Alameda County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Mar 2011 (completed)
  2. ConsentedAug 2014 (completed)
  3. Construction (completed)
  4. OperatingDec 2015 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
709
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Tesla Sub 115 KV
Location
Alameda County, California
Technology
Wind: 36.0 MW
Total requested
36.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
31 March 2011
Agreement signed
19 August 2014
Proposed online date
December 2013
Came online
December 2015

Location

Marker shows the centre of Alameda County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Alameda County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem