United States › Grid › Interconnection queues › California

SOLAR · CAISO

Frontier Solar

Frontier Solar is a 20.0 MW solar request built and operating in the CAISO interconnection queue, in Kern County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Mar 2011 (completed)
  2. ConsentedJan 2014 (completed)
  3. Construction (completed)
  4. OperatingFeb 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
705
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Arco-Carneras 70 kV line
Location
Kern County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
31 March 2011
Agreement signed
24 January 2014
Proposed online date
September 2013
Came online
February 2019

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County