SOLAR · WEST

Solar project Q19, Kern County

Solar project Q19, Kern County is a 250 MW solar request built and operating in the West interconnection queue, in Kern County, California, connecting to Los Angeles Department of Water and Power.

Queue statusOperating
  1. PlanningQueued Sep 2011 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingSep 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Q19
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
Beacon 230 kV Sw Station
Location
Kern County, California
Technology
Solar: 250 MW
Total requested
250 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
19 September 2011
Proposed online date
June 2016
Came online
September 2016

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.