United States โ€บ Grid โ€บ Interconnection queues โ€บ Arizona

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in Arizona (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4824.2 GW
Active in queue24.2 GW48 requests
Agreement signed300 MW1 requests
Withdrawn9038.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

48 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Jove Solar
Solar + storage
4,133 MWIn study La Paz, AZCAISO Apr 2021target 2030
Bouse Solar And Storage Plant
Solar + storage
2,021 MWIn study La Paz, AZCAISO Apr 2021target 2033
Ranegras PVS
Solar + storage
1,438 MWIn study La Paz, AZCAISO Apr 2021target 2029
Solar + storage project Q379, Maricopa County
Solar + storage
1,000 MWPaused / redesign Maricopa, AZWest Mar 2021target 2024
Harquahala Flats 2
Solar + storage
822 MWIn study Maricopa, AZCAISO Apr 2021target 2028
Other project 103, Apache County
Other
768 MWIn study Apache, AZWest Nov 2021target 2024
Socorro Peak Solar
Solar + storage
756 MWIn study La Paz, AZCAISO Apr 2021target 2029
Solar + storage project Q402, Navajo County
Solar + storage
750 MWIn study Navajo, AZWest Sep 2021target 2025
Solar + storage project Q401, Coconino County
Solar + storage
700 MWIn study Coconino, AZWest Sep 2021target 2026
Solar + storage project 93, Apache County
Solar + storage
700 MWIn study Apache, AZWest Apr 2021target 2021
Remy
Solar + storage
617 MWIn study Yuma, AZCAISO Apr 2021target 2029
Solar + storage project 90, Pima County
Solar + storage
600 MWIn study Pima, AZWest Jan 2021target 2025
Solar + storage project Q387, Navajo County
Solar + storage
588 MWIn study Navajo, AZWest Mar 2021target 2025
Solar + storage project Q29, Maricopa County
Solar + storage
500 MWIn study Maricopa, AZWest Jun 2021target 2027
Onshore wind project NC5-008, Mohave County
Onshore wind
500 MWIn study Mohave, AZWest May 2021target 2025
Solar + storage project Q393, Coconino County
Solar + storage
500 MWIn study Coconino, AZWest Mar 2021target 2024
Solar + storage project Q368, Yuma County
Solar + storage
500 MWIn study Yuma, AZWest Mar 2021target 2026
Solar + storage project 2021-G4, Pinal County
Solar + storage
463 MWIn study Pinal, AZWest Apr 2021target 2023
Alisa Solar Energy Complex
Solar + storage
417 MWIn study Yuma, AZCAISO Apr 2021target 2028
Other project 107, Pima County
Other
400 MWIn study Pima, AZWest Dec 2021target 2024
Gas project Q76, Pinal County
Gas
332 MWIn study Pinal, AZWest May 2021target 2026
Harquahala Sunrise 2
Solar + storage
330 MWIn study Maricopa, AZCAISO Apr 2021target 2026
Solar + storage project Q388, Pinal County
Solar + storage
323 MWIn study Pinal, AZWest Mar 2021target 2025
Other project 106, Pima County
Other
320 MWIn study Pima, AZWest Dec 2021target 2024
Onshore wind project Q370, Coconino County
Onshore wind
310 MWIn study Coconino, AZWest Mar 2021target 2024
Battery storage project Q375, Maricopa County
Battery storage
300 MWAgreement signed Maricopa, AZWest Mar 2021target 2023
Solar + storage project Q437, Maricopa County
Solar + storage
300 MWIn study Maricopa, AZWest Sep 2021target 2024
Solar + storage project Q392, Pinal County
Solar + storage
270 MWIn study Pinal, AZWest Mar 2021target 2024
Other project 100, Pima County
Other
250 MWIn study Pima, AZWest Oct 2021target 2024
Solar + storage project Q377, Maricopa County
Solar + storage
250 MWPaused / redesign Maricopa, AZWest Mar 2021target 2024
Battery storage project Q427, Maricopa County
Battery storage
250 MWIn study Maricopa, AZWest Sep 2021target 2025
Solar + storage project Q378, Maricopa County
Solar + storage
250 MWPaused / redesign Maricopa, AZWest Mar 2021target 2024
Other project 95, Apache County
Other
250 MWIn study Apache, AZWest Jun 2021target 2024
Other project 98, Pinal County
Other
241 MWIn study Pinal, AZWest Sep 2021target 2025
Solar + storage project Q424, Navajo County
Solar + storage
200 MWIn study Navajo, AZWest Sep 2021target 2025
Battery storage project Q409, Maricopa County
Battery storage
200 MWIn study Maricopa, AZWest Sep 2021target 2025
Other project 110, Pima County
Other ยท TEP
200 MWIn study Pima, AZWest Dec 2021target 2024
Solar + storage project Q425, Yuma County
Solar + storage
200 MWIn study Yuma, AZWest Sep 2021target 2024
Battery storage project Q422, Navajo County
Battery storage
200 MWIn study Navajo, AZWest Sep 2021target 2025
Other project 109, Pima County
Other ยท TEP
200 MWIn study Pima, AZWest Dec 2021target 2024
Other project 108, Pima County
Other ยท TEP
200 MWIn study Pima, AZWest Dec 2021target 2024
Onshore wind project 2021-G6, Yavapai County
Onshore wind
135 MWIn study Yavapai, AZWest Jun 2021target 2025
Battery storage project Q423, Navajo County
Battery storage
125 MWIn study Navajo, AZWest Sep 2021target 2025
Battery storage project Q384, Maricopa County
Battery storage
125 MWPaused / redesign Maricopa, AZWest Mar 2021target 2025
Solar + storage project 2021-G3, Pinal County
Solar + storage
119 MWIn study Pinal, AZWest Apr 2021target 2023
Battery storage project Q372, Maricopa County
Battery storage
100 MWIn study Maricopa, AZWest Mar 2021target 2024
Gas project Q81, Maricopa County
Gas
30.0 MWIn study Maricopa, AZWest Jun 2021target 2025
Other project Q394, Maricopa County
Other
5.0 MWIn study Maricopa, AZWest Mar 2021target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)