Withdrawn queue requests in Arizona (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8134.3 GW
Active in queue14.6 GW36 requests
Agreement signed0.0 MW0 requests
Withdrawn8134.3 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

81 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
BlueWater Solar
Solar + storage
2,031 MWWithdrawn / abandoned La Paz, AZCAISO Apr 2023target 2028
Solar + storage project Q109, Navajo County
Solar + storage
2,000 MWWithdrawn / abandoned Navajo, AZWest Jul 2023target 2027
Solar + storage project Q33, Pinal County
Solar + storage
2,000 MWWithdrawn / abandoned Pinal, AZWest Oct 2023target 2028
Icarus Solar
Solar + storage
1,435 MWWithdrawn / abandoned Mohave, AZCAISO Apr 2023target 2032
Other project 156, Pima County
Other
1,000 MWWithdrawn / abandoned Pima, AZWest Apr 2023target 2027
Solar + storage project Q508, Maricopa County
Solar + storage
1,000 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2028
Other project 157, Pima County
Other
1,000 MWWithdrawn / abandoned Pima, AZWest Apr 2023target 2027
Solar + storage project Q102, Mohave County
Solar + storage
930 MWWithdrawn / abandoned Mohave, AZWest Apr 2023target 2027
Other project 155, Cochise County
Other
800 MWWithdrawn / abandoned Cochise, AZWest Apr 2023target 2027
Solar + storage project Q14, Maricopa County
Solar + storage
800 MWWithdrawn / abandoned Maricopa, AZWest Apr 2023target 2028
Other project Q512, Mohave County
Other
700 MWWithdrawn / abandoned Mohave, AZWest Mar 2023target 2027
Solar + storage project Q506, Maricopa County
Solar + storage
660 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2027
Solar + storage project Q110, Navajo County
Solar + storage
600 MWWithdrawn / abandoned Navajo, AZWest Sep 2023target 2027
Other project 154, Cochise County
Other
600 MWWithdrawn / abandoned Cochise, AZWest Apr 2023target 2027
Pinecone
Battery storage
515 MWWithdrawn / abandoned Yuma, AZCAISO Apr 2023target 2028
Battery storage project Q511, Coconino County
Battery storage
500 MWWithdrawn / abandoned Coconino, AZWest Mar 2023target 2028
Solar + storage project 162, Cochise County
Solar + storage
500 MWWithdrawn / abandoned Cochise, AZWest Sep 2023target 2030
Solar + storage project Q495, Yuma County
Solar + storage
500 MWWithdrawn / abandoned Yuma, AZWest Mar 2023target 2028
Other project Q544, Navajo County
Other
500 MWWithdrawn / abandoned Navajo, AZWest Sep 2023target 2026
Other project Q532, Coconino County
Other
500 MWWithdrawn / abandoned Coconino, AZWest Apr 2023target 2027
Solar + storage project 158, Pinal County
Solar + storage
500 MWWithdrawn / abandoned Pinal, AZWest Aug 2023target 2030
Battery storage project 153, Pima County
Battery storage
500 MWWithdrawn / abandoned Pima, AZWest Mar 2023target 2028
Battery storage project 159, Pinal County
Battery storage
500 MWWithdrawn / abandoned Pinal, AZWest Aug 2023target 2030
Battery storage project Q510, Yuma County
Battery storage
500 MWWithdrawn / abandoned Yuma, AZWest Mar 2023target 2028
Solar + storage project 161, Cochise County
Solar + storage
500 MWWithdrawn / abandoned Cochise, AZWest Sep 2023target 2030
Other project Q533, Coconino County
Other
500 MWWithdrawn / abandoned Coconino, AZWest Apr 2023target 2027
Battery storage project Q04, Maricopa County
Battery storage
500 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2028
Solar + storage project Q531, Maricopa County
Solar + storage
441 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2027
Solar + storage project Q515, Yuma County
Solar + storage
400 MWWithdrawn / abandoned Yuma, AZWest Mar 2023target 2027
Battery storage project Q105, Pinal County
Battery storage
400 MWWithdrawn / abandoned Pinal, AZWest May 2023target 2027
Battery storage project Q542, Maricopa County
Battery storage
400 MWWithdrawn / abandoned Maricopa, AZWest Sep 2023target 2026
Other project 149, Apache County
Other
400 MWWithdrawn / abandoned Apache, AZWest Feb 2023target 2028
Solar + storage project Q527, Coconino County
Solar + storage
400 MWWithdrawn / abandoned Coconino, AZWest Mar 2023target 2027
Solar + storage project Q545, Yavapai County
Solar + storage
360 MWWithdrawn / abandoned Yavapai, AZWest Sep 2023target 2027
Solar + storage project Q501, Pinal County
Solar + storage
350 MWWithdrawn / abandoned Pinal, AZWest Mar 2023target 2027
Gas project Q39, Maricopa County
Gas
350 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2027
Battery storage project Q530, Maricopa County
Battery storage
350 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2026
Other project Q541, Maricopa County
Other
330 MWWithdrawn / abandoned Maricopa, AZWest Sep 2023target 2026
Battery storage project Q503, Maricopa County
Battery storage
321 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2027
Battery storage project Q535, Maricopa County
Battery storage
310 MWWithdrawn / abandoned Maricopa, AZWest Aug 2023target 2028
Solar + storage project Q513, Yuma County
Solar + storage
300 MWWithdrawn / abandoned Yuma, AZWest Mar 2023target 2026
Solar + storage project Q516, Pinal County
Solar + storage
300 MWWithdrawn / abandoned Pinal, AZWest Mar 2023target 2027
Onshore wind project Q525, Mohave County
Onshore wind
300 MWWithdrawn / abandoned Mohave, AZWest Mar 2023target 2027
Solar + storage project Q514, Yuma County
Solar + storage
300 MWWithdrawn / abandoned Yuma, AZWest Mar 2023target 2026
Onshore wind project 163, Apache County
Onshore wind
300 MWWithdrawn / abandoned Apache, AZWest Sep 2023target 2028
Solar + storage project 150, Cochise County
Solar + storage
300 MWWithdrawn / abandoned Cochise, AZWest Feb 2023target 2027
Gas project Q30, Pinal County
Gas
297 MWWithdrawn / abandoned Pinal, AZWest Apr 2023target 2026
Battery storage project Q536, Pinal County
Battery storage
259 MWWithdrawn / abandoned Pinal, AZWest Aug 2023target 2028
Battery storage project Q521, Maricopa County
Battery storage
250 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2027
Solar project Q500, Maricopa County
Solar
250 MWWithdrawn / abandoned Maricopa, AZWest Mar 2023target 2024
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)