United States β€Ί Grid β€Ί Interconnection queues β€Ί Colorado

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Colorado, West

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown36173.0 GW
Active in queue43.2 GW209 requests
Agreement signed11.0 GW60 requests
Withdrawn36173.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

361 requests Β· page 1 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Other project GI-2018-30, Park County
Other
1,007 MWWithdrawn / abandoned Park, COWest Aug 2018target 2022
Other project GI-2020-07, Pueblo County
Other
1,000 MWWithdrawn / abandoned Pueblo, COWest Mar 2020target 2023
Onshore wind project GI-2017-47, Kiowa County
Onshore wind
1,000 MWWithdrawn / abandoned Kiowa, COWest Nov 2017target 2020
Onshore wind project GI-2008-15, Baca County
Onshore wind
800 MWWithdrawn / abandoned Baca, COWest Aug 2008target 2013
Coal project GI-2003-5, Morgan County
Coal
750 MWWithdrawn / abandoned Morgan, COWest Dec 2003target 2009
Solar + storage project GI-2023-17, Crowley County
Solar + storage
750 MWWithdrawn / abandoned Crowley, COWest May 2023target 2027
Onshore wind project GI-2018-5, Baca County
Onshore wind
700 MWWithdrawn / abandoned Baca, COWest Mar 2018target 2020
Onshore wind project GI-2018-4, Baca County
Onshore wind
700 MWWithdrawn / abandoned Baca, COWest Mar 2018target 2020
Onshore wind project GI-2020-14, Cheyenne County
Onshore wind
700 MWWithdrawn / abandoned Cheyenne, COWest Sep 2020target 2024
Coal project GI-2007-1, Morgan County
Coal
675 MWWithdrawn / abandoned Morgan, COWest Mar 2007target 2014
Coal project GI-2007-2, Bent County
Coal
675 MWWithdrawn / abandoned Bent, COWest Mar 2007target 2014
Gas project GI-2008-1, Denver County
Gas
675 MWWithdrawn / abandoned Denver, COWest Feb 2008target 2013
Gas project GI-2008-7, Morgan County
Gas
650 MWWithdrawn / abandoned Morgan, COWest Jun 2008target 2013
Onshore wind project GI-2016-27, Elbert County
Onshore wind
640 MWWithdrawn / abandoned Elbert, COWest Nov 2016target 2019
Onshore wind project GI-2017-24, Morgan County
Onshore wind
630 MWWithdrawn / abandoned Morgan, COWest Jul 2017target 2020
Coal project GI-2006-3, Morgan County
Coal
600 MWWithdrawn / abandoned Morgan, COWest Oct 2006target 2013
Onshore wind project GI-2016-6, Lincoln County
Onshore wind
600 MWWithdrawn / abandoned Lincoln, COWest Apr 2016target 2018
Onshore wind project GI-2017-20, Kiowa County
Onshore wind
600 MWWithdrawn / abandoned Kiowa, COWest Jun 2017target 2020
Solar project GI-2017-38, Arapahoe County
Solar
575 MWWithdrawn / abandoned Arapahoe, COWest Sep 2017target 2023
Solar project GI-2017-37, Pueblo County
Solar
575 MWWithdrawn / abandoned Pueblo, COWest Sep 2017target 2023
Onshore wind project GI-2016-25, Kit Carson County
Onshore wind
500 MWWithdrawn / abandoned Kit Carson, COWest Oct 2016target 2020
Onshore wind project GI-2021-19, Pueblo County
Onshore wind
500 MWWithdrawn / abandoned Pueblo, COWest Sep 2021target 2025
Onshore wind project GI-2008-5, Kiowa County
Onshore wind
500 MWWithdrawn / abandoned Kiowa, COWest May 2008target 2016
Onshore wind project GI-2008-22, Las Animas County
Onshore wind
500 MWWithdrawn / abandoned Las Animas, COWest Oct 2008target 2010
Solar project GI-2017-49, Pueblo County
Solar
500 MWWithdrawn / abandoned Pueblo, COWest Nov 2017target 2022
Onshore wind project GI-2021-20, Pueblo County
Onshore wind
500 MWWithdrawn / abandoned Pueblo, COWest Sep 2021target 2025
Onshore wind project GI-2010-21, Kit Carson County
Onshore wind
500 MWWithdrawn / abandoned Kit Carson, COWest Dec 2010target 2014
Coal project GI-2003-2, Elbert County
Coal
500 MWWithdrawn / abandoned Elbert, COWest Nov 2003target 2008
Solar project GI-2017-46, Huerfano County
Solar
500 MWWithdrawn / abandoned Huerfano, COWest Nov 2017target 2020
Solar project GI-2021-30, Morgan County
Solar
500 MWWithdrawn / abandoned Morgan, COWest Oct 2021target 2024
Solar project GI-2017-11, Lincoln County
Solar
500 MWWithdrawn / abandoned Lincoln, COWest Mar 2017target 2020
Onshore wind project GI-2008-19, Prowers County
Onshore wind
500 MWWithdrawn / abandoned Prowers, COWest Sep 2008target 2011
Onshore wind project GI-2017-26, Bent County
Onshore wind
500 MWWithdrawn / abandoned Bent, COWest Aug 2017target 2020
Solar project GI-2016-9, Alamosa County
Solar
480 MWWithdrawn / abandoned Alamosa, COWest Apr 2016target 2023
Onshore wind project GI-2008-10, Morgan County
Onshore wind
450 MWWithdrawn / abandoned Morgan, COWest Jun 2008target 2011
Solar project GI-2019-1, El Paso County
Solar
450 MWWithdrawn / abandoned El Paso, COWest Feb 2019target 2021
Onshore wind project GI-2004-5, Weld County
Onshore wind
402 MWWithdrawn / abandoned Weld, COWest Aug 2004target 2006
Onshore wind project GI-2023-15, Morgan County
Onshore wind
401 MWWithdrawn / abandoned Morgan, COWest May 2023target 2026
Onshore wind project GI-2017-44, Huerfano County
Onshore wind
400 MWWithdrawn / abandoned Huerfano, COWest Nov 2017target 2020
Solar + storage project GI-2021-8, Morgan County
Solar + storage
400 MWWithdrawn / abandoned Morgan, COWest Apr 2021target 2025
Solar project GI-2017-13, Arapahoe County
Solar
400 MWWithdrawn / abandoned Arapahoe, COWest Apr 2017target 2020
Onshore wind project GI-2010-17, Kit Carson County
Onshore wind
400 MWWithdrawn / abandoned Kit Carson, COWest Nov 2010target 2014
Onshore wind project GI-2008-24, Huerfano County
Onshore wind
400 MWWithdrawn / abandoned Huerfano, COWest Oct 2008target 2012
Onshore wind project GI-2008-8, Sedgwick County
Onshore wind
400 MWWithdrawn / abandoned Sedgwick, COWest Jun 2008target 2010
Onshore wind project GI-2017-43, Huerfano County
Onshore wind
400 MWWithdrawn / abandoned Huerfano, COWest Nov 2017target 2020
Solar project GI-2017-35, Pueblo County
Solar
400 MWWithdrawn / abandoned Pueblo, COWest Sep 2017target 2020
Solar + storage project GI-2022-10, Pueblo County
Solar + storage
400 MWWithdrawn / abandoned Pueblo, COWest Apr 2022target 2025
Onshore wind project GI-2008-13, Sedgwick County
Onshore wind
400 MWWithdrawn / abandoned Sedgwick, COWest Jul 2008target 2011
Onshore wind project GI-2020-12, Elbert County
Onshore wind
400 MWWithdrawn / abandoned Elbert, COWest Sep 2020target 2024
Onshore wind project GI-2008-14, Sedgwick County
Onshore wind
400 MWWithdrawn / abandoned Sedgwick, COWest Jul 2008target 2011
Page 1 of 8

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)