United States βΊ Grid βΊ Interconnection queues βΊ Colorado
ONSHORE WIND Β· WESTOnshore wind project GI-2016-6, Lincoln County
Onshore wind project GI-2016-6, Lincoln County is a 600 MW onshore wind request withdrawn in the West interconnection queue, in Lincoln County, Colorado, connecting to Public Service Company Of Colorado.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2016 (completed)
- Withdrawn / abandonedNov 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-2016-6
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company Of Colorado
- Connection point (POI)
- Missile Site Substation
- Location
- Lincoln County, Colorado
- Technology
- Wind: 600 MW
- Total requested
- 600 MW
- Service type
- Energy only (ERIS)
- Study phase
- Feasibility Study Complete System Impact Study Complete Request Withdrawn 11/2/2018
- Queue status
- Withdrawn
- Entered queue
- 25 April 2016
- Proposed online date
- December 2018
- Withdrawn
- November 2020
Location
Marker shows the centre of Lincoln County; the queue data does not give exact sites.
Other requests in Lincoln County
- Onshore wind project GI-2016-3, Lincoln CountyOnshore wind Β· 600 MW Β· agreement signed
- Onshore wind project GI-2016-4, Lincoln CountyOnshore wind Β· 300 MW Β· agreement signed
- Onshore wind project GI-2007-13, Lincoln CountyOnshore wind Β· 250 MW Β· agreement signed
- Onshore wind project GI-2011-7, Lincoln CountyOnshore wind Β· 200 MW Β· agreement signed
- Onshore wind project GI-2011-2, Lincoln CountyOnshore wind Β· 200 MW Β· agreement signed
- Onshore wind project GI-DISIS-2022-29, Lincoln CountyOnshore wind Β· 200 MW Β· agreement signed
- Onshore wind project CSUT-2025-1, Lincoln CountyOnshore wind Β· 500 MW Β· in study
- Solar + storage project GI-2024-20, Lincoln CountySolar + storage Β· 199 MW Β· in study
- Solar + storage project GI-2024-19, Lincoln CountySolar + storage Β· 199 MW Β· in study
- Onshore wind project GI-CS-2025-11, Lincoln CountyOnshore wind Β· 199 MW Β· in study
- Solar + storage project GI-TC-2024-02, Lincoln CountySolar + storage Β· 150 MW Β· in study
- Solar + storage project GI-TC-2024-01, Lincoln CountySolar + storage Β· 150 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem