COAL Β· WESTCoal project GI-2007-1, Morgan County
Coal project GI-2007-1, Morgan County is a 675 MW coal request withdrawn in the West interconnection queue, in Morgan County, Colorado, connecting to Public Service Company Of Colorado.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2007 (completed)
- Withdrawn / abandonedNov 2007 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GI-2007-1
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Public Service Company Of Colorado
- Connection point (POI)
- Pawnee Substation
- Location
- Morgan County, Colorado
- Technology
- Coal: 675 MW
- Total requested
- 675 MW
- Service type
- Network resource (NRIS)
- Study phase
- Request Withdrawn 11/8/07
- Queue status
- Withdrawn
- Entered queue
- 7 March 2007
- Proposed online date
- May 2014
- Withdrawn
- November 2007
Location
Marker shows the centre of Morgan County; the queue data does not give exact sites.
Other requests in Morgan County
- Solar + storage project GI-TC-2024-30, Morgan CountySolar + storage Β· 400 MW Β· agreement signed
- Solar + storage project GI-2024-06, Morgan CountySolar + storage Β· 500 MW Β· in study
- Solar + storage project GI-2025-07, Morgan CountySolar + storage Β· 360 MW Β· in study
- Solar + storage project GI-2025-01, Morgan CountySolar + storage Β· 300 MW Β· in study
- Battery storage project 5RSC-2024-11, Morgan CountyBattery storage Β· 250 MW Β· in study
- Solar + storage project 5RSC-2024-27, Morgan CountySolar + storage Β· 250 MW Β· in study
- Solar + storage project GI-CS-2025-20, Morgan CountySolar + storage Β· 200 MW Β· in study
- Solar + storage project GI-CS-2025-19, Morgan CountySolar + storage Β· 200 MW Β· in study
- Solar project GI-2024-18, Morgan CountySolar Β· 150 MW Β· in study
- Onshore wind project GI-2023-14, Morgan CountyOnshore wind Β· 400 MW Β· suspended
- Coal project GI-2003-5, Morgan CountyCoal Β· 750 MW Β· withdrawn
- Gas project GI-2008-7, Morgan CountyGas Β· 650 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem