πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Southeast (non-ISO utilities) (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown33140.7 GW
Active in queue24.0 GW210 requests
Agreement signed5,748 MW37 requests
Withdrawn33140.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

331 requests Β· page 1 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 564, Trousdale County
Gas
1,224 MWWithdrawn / abandoned Trousdale, TNSoutheast Jun 2023target 2028
Gas project 565, Trousdale County
Gas
1,098 MWWithdrawn / abandoned Trousdale, TNSoutheast Jun 2023target 2028
Gas project 567, Cheatham County
Gas
990 MWWithdrawn / abandoned Cheatham, TNSoutheast Jun 2023target 2027
Gas project IC-1219, Hart County
Gas
640 MWWithdrawn / abandoned Hart, GASoutheast Dec 2023
Gas project IC-1218, Lee County
Gas
640 MWWithdrawn / abandoned Lee, ALSoutheast Dec 2023
Gas project 575, Lowndes County
Gas
620 MWWithdrawn / abandoned Lowndes, MSSoutheast Jul 2023
Solar project 597, Mississippi County
Solar
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023
Battery storage project IC-1117, Fulton County
Battery storage
500 MWWithdrawn / abandoned Fulton, GASoutheast Feb 2023
Onshore wind project GI-113, Randolph County
Onshore wind
500 MWWithdrawn / abandoned Randolph, MOSoutheast Jan 2023target 2026
Solar + storage project 592, Mississippi County
Solar + storage
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023target 2027
Solar + storage project 594, Mississippi County
Solar + storage
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023target 2027
Solar + storage project 593, Mississippi County
Solar + storage
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023target 2027
Solar project 599, Mississippi County
Solar
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023
Solar project 598, Mississippi County
Solar
500 MWWithdrawn / abandoned Mississippi, ARSoutheast Dec 2023
Onshore wind project GI-114, Randolph County
Onshore wind
500 MWWithdrawn / abandoned Randolph, MOSoutheast Jan 2023target 2026
Gas project IC-1217, Jackson County
Gas
490 MWWithdrawn / abandoned Jackson, GASoutheast Dec 2023
Gas project 566, Haywood County
Gas
415 MWWithdrawn / abandoned Haywood, TNSoutheast Jun 2023
Battery storage project 899003, Chatham County
Battery storage Β· Masked
350 MWWithdrawn / abandoned Chatham, NCSoutheast Jun 2023
Solar project IC-1183, Mcduffie County
Solar
250 MWWithdrawn / abandoned Mcduffie, GASoutheast Oct 2023target 2026
Battery storage project 232, Dillon County
Battery storage
250 MWWithdrawn / abandoned Dillon, SCSoutheast Jun 2023target 2027
Solar + storage project 220, Georgetown County
Solar + storage
250 MWWithdrawn / abandoned Georgetown, SCSoutheast Jun 2023target 2028
Solar project IC-1192, Burke County
Solar
245 MWWithdrawn / abandoned Burke, GASoutheast Oct 2023target 2027
Solar project 601, Monroe County
Solar
240 MWWithdrawn / abandoned Monroe, ALSoutheast Dec 2023
Solar project 602, Monroe County
Solar
240 MWWithdrawn / abandoned Monroe, MSSoutheast Dec 2023
Solar project 572, Rankin County
Solar
240 MWWithdrawn / abandoned Rankin, MSSoutheast Jun 2023target 2026
Solar + storage project 577, Oktibbeha County
Solar + storage
230 MWWithdrawn / abandoned Oktibbeha, MSSoutheast Jul 2023target 2029
Solar project 602, Union County
Solar Β· Third Party
225 MWWithdrawn / abandoned Union, FLSoutheast Nov 2023target 2027
Solar project 604, Lowndes County
Solar
224 MWWithdrawn / abandoned Lowndes, MSSoutheast Dec 2023
Solar project 585, Chickasaw County
Solar
220 MWWithdrawn / abandoned Chickasaw, MSSoutheast Sep 2023target 2027
Solar project 219, Georgetown County
Solar
213 MWWithdrawn / abandoned Georgetown, SCSoutheast Jun 2023target 2028
Battery storage project 574, Montgomery County
Battery storage
200 MWWithdrawn / abandoned Montgomery, TNSoutheast Jun 2023
Solar + storage project 542, Pontotoc County
Solar + storage
200 MWWithdrawn / abandoned Pontotoc, MSSoutheast Apr 2023target 2027
Solar + storage project IC-1196, Jasper County
Solar + storage
200 MWWithdrawn / abandoned Jasper, GASoutheast Oct 2023target 2025
Solar + storage project IC-1205, Jasper County
Solar + storage
200 MWWithdrawn / abandoned Jasper, MSSoutheast Nov 2023target 2027
Solar project 188, Marion County
Solar
200 MWWithdrawn / abandoned Marion, SCSoutheast Jun 2023target 2024
Solar project IC-1164, Mobile County
Solar
200 MWWithdrawn / abandoned Mobile, ALSoutheast Aug 2023target 2027
Battery storage project IC-1175, Etowah County
Battery storage
200 MWWithdrawn / abandoned Etowah, ALSoutheast Sep 2023target 2027
Solar project IC-1221, Hart County
Solar
200 MWWithdrawn / abandoned Hart, GASoutheast Dec 2023
Solar + storage project IC-1173, Talladega County
Solar + storage
200 MWWithdrawn / abandoned Talladega, ALSoutheast Sep 2023target 2026
Battery storage project IC-1215, Fulton County
Battery storage
200 MWWithdrawn / abandoned Fulton, GASoutheast Dec 2023
Solar project IC-1190, Putnam County
Solar
200 MWWithdrawn / abandoned Putnam, GASoutheast Oct 2023target 2028
Battery storage project IC-1119, Bartow County
Battery storage
200 MWWithdrawn / abandoned Bartow, GASoutheast Feb 2023
Solar + storage project 539, Chickasaw County
Solar + storage
200 MWWithdrawn / abandoned Chickasaw, MSSoutheast Apr 2023target 2028
Solar project IC-1193, Hancock County
Solar
200 MWWithdrawn / abandoned Hancock, GASoutheast Oct 2023target 2028
Onshore wind project 537, Gibson County
Onshore wind
200 MWWithdrawn / abandoned Gibson, TNSoutheast Mar 2023target 2024
Solar + storage project 531, Mcnairy County
Solar + storage
200 MWWithdrawn / abandoned Mcnairy, TNSoutheast Mar 2023
Solar + storage project IC-1169, Lowndes County
Solar + storage
200 MWWithdrawn / abandoned Lowndes, ALSoutheast Aug 2023target 2027
Solar project IC-1191, Putnam County
Solar
200 MWWithdrawn / abandoned Putnam, GASoutheast Oct 2023target 2028
Solar + storage project IC-1141, Lamar County
Solar + storage
200 MWWithdrawn / abandoned Lamar, MSSoutheast May 2023target 2027
Solar project IC-1194, Hart County
Solar
200 MWWithdrawn / abandoned Hart, GASoutheast Oct 2023target 2028
Page 1 of 7

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)