πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Alabama

SOLAR + STORAGE Β· SOUTHEAST

Solar + storage project IC-1173, Talladega County

Solar + storage project IC-1173, Talladega County is a 200 MW solar + storage request withdrawn in the Southeast interconnection queue, in Talladega County, Alabama, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2023 (completed)
  2. Withdrawn / abandonedMay 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-1173
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Bynum - Jackson Shoals 115 kV Line
Location
Talladega County, Alabama
Technology
Solar: 200 MW Β· Battery
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
19 September 2023
Proposed online date
November 2026
Withdrawn
May 2024

Location

Marker shows the centre of Talladega County; the queue data does not give exact sites.

Power plants in Alabama Β· Transmission lines in Alabama

Other requests in Talladega County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem