United States βΊ Grid βΊ Interconnection queues βΊ Alabama
SOLAR Β· SOUTHEASTSolar project IC-1011, Talladega County
Solar project IC-1011, Talladega County is a 33.5 MW solar request withdrawn in the Southeast interconnection queue, in Talladega County, Alabama, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2022 (completed)
- Withdrawn / abandonedOct 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-1011
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Talladega - East Talladega DS 46 kV Line
- Location
- Talladega County, Alabama
- Technology
- Solar: 33.5 MW
- Total requested
- 33.5 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 21 January 2022
- Withdrawn
- October 2022
Location
Marker shows the centre of Talladega County; the queue data does not give exact sites.
Other requests in Talladega County
- Solar project IC-1162, Talladega CountySolar Β· 100 MW Β· suspended
- Solar project IC-943, Talladega CountySolar Β· 80.0 MW Β· suspended
- AMEA-SylacaugaGas Β· 90.0 MW Β· built
- Gas project IC-050, Talladega CountyGas Β· 1,800 MW Β· withdrawn
- Gas project IC-055, Talladega CountyGas Β· 888 MW Β· withdrawn
- Gas project IC-133, Talladega CountyGas Β· 828 MW Β· withdrawn
- Solar + storage project IC-1173, Talladega CountySolar + storage Β· 200 MW Β· withdrawn
- Solar + storage project IC-887, Talladega CountySolar + storage Β· 80.0 MW Β· withdrawn
- Solar project IC-572, Talladega CountySolar Β· 59.5 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem