United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Southeast (non-ISO utilities) (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown375,748 MW
Active in queue24.0 GW210 requests
Agreement signed5,748 MW37 requests
Withdrawn33140.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

37 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project LGE-GIS-2023-002, Mercer County
Gas
660 MWAgreement signed Mercer, KYSoutheast Apr 2023target 2030
Gas project IC-1166, Coweta County
Gas
411 MWAgreement signed Coweta, GASoutheast Aug 2023target 2025
Gas project IC-1168, Coweta County
Gas
411 MWAgreement signed Coweta, GASoutheast Aug 2023target 2025
Gas project IC-1167, Coweta County
Gas
411 MWAgreement signed Coweta, GASoutheast Aug 2023target 2025
Battery storage project 897163, Wayne County
Battery storage Β· Duke Energy Progress, LLC - HF Lee Energy - Storage
260 MWAgreement signed Wayne, NCSoutheast Jun 2023
Battery storage project IC-1223, Hall County
Battery storage
250 MWAgreement signed Hall, GASoutheast Dec 2023target 2028
Battery storage project IC-1222, Bartow County
Battery storage
250 MWAgreement signed Bartow, GASoutheast Dec 2023target 2027
Solar project IC-1206, Laurens County
Solar
225 MWAgreement signed Laurens, GASoutheast Nov 2023target 2028
Battery storage project IC-1187, Wilkinson County
Battery storage
220 MWAgreement signed Wilkinson, GASoutheast Oct 2023target 2027
Solar project IC-1195, Warren County
Solar
200 MWAgreement signed Warren, GASoutheast Oct 2023target 2028
Solar project IC-1204, Jefferson County
Solar
200 MWAgreement signed Jefferson, GASoutheast Nov 2023target 2028
Solar project IC-1152, Washington County
Solar
200 MWAgreement signed Washington, GASoutheast Jul 2023target 2027
Battery storage project 898999, Robeson County
Battery storage Β· Masked
200 MWAgreement signed Robeson, NCSoutheast Jun 2023
Solar project IC-1142, Baldwin County
Solar
183 MWAgreement signed Baldwin, GASoutheast May 2023target 2028
Solar project IC-1145, Jasper County
Solar
156 MWAgreement signed Jasper, MSSoutheast Jun 2023target 2028
Battery storage project IC-1210, Walker County
Battery storage
150 MWAgreement signed Walker, ALSoutheast Dec 2023target 2026
Solar + storage project 538, Henderson County
Solar + storage
150 MWAgreement signed Henderson, TNSoutheast Mar 2023target 2029
Gas project 899759, Catawba County
Gas
136 MWAgreement signed Catawba, NCSoutheast Jun 2023target 2028
Solar project IC-1172, Jefferson County
Solar
128 MWAgreement signed Jefferson, GASoutheast Sep 2023target 2028
Battery storage project 899053, Wilkes County
Battery storage
120 MWAgreement signed Wilkes, NCSoutheast Jun 2023
Battery storage project IC-1116, Carroll County
Battery storage
100 MWAgreement signed Carroll, GASoutheast Jan 2023target 2027
Solar + storage project 530, Pinola County
Solar + storage
90.0 MWAgreement signed Pinola, MSSoutheast Mar 2023target 2028
Solar project 917443, Scotland County
Solar
80.0 MWAgreement signed Scotland, NCSoutheast Sep 2023
Solar project IC-1128, Perry County
Solar
79.9 MWAgreement signed Perry, ALSoutheast Mar 2023target 2027
Solar project IC-1127, Perry County
Solar
79.9 MWAgreement signed Perry, ALSoutheast Mar 2023target 2027
Solar project 920665, Union County
Solar
75.0 MWAgreement signed Union, SCSoutheast Sep 2023
Solar project 920659, Wayne County
Solar
67.0 MWAgreement signed Wayne, NCSoutheast Sep 2023
Gas project 899591, Richmond County
Gas Β· Duke Energy Progress, LLC
46.8 MWAgreement signed Richmond, NCSoutheast Jun 2023
Gas project GI-117, New Madrid County
Gas
46.0 MWAgreement signed New Madrid, MOSoutheast May 2023target 2024
Solar project IC-1203, Jasper County
Solar
44.0 MWAgreement signed Jasper, MSSoutheast Nov 2023target 2028
Solar project 919551, Lincoln County
Solar
40.0 MWAgreement signed Lincoln, NCSoutheast Sep 2023
Gas project 904269, Wayne County
Gas Β· Duke Energy Progress, LLC
26.0 MWAgreement signed Wayne, NCSoutheast Jun 2023
Gas project GI-116, New Madrid County
Gas
26.0 MWAgreement signed New Madrid, MOSoutheast May 2023target 2024
Gas project 899581, Wayne County
Gas Β· Duke Energy Progress, LLC
20.0 MWAgreement signed Wayne, NCSoutheast Jun 2023
Solar + storage project IC-1199, Lowndes County
Solar + storage
3.5 MWAgreement signed Lowndes, GASoutheast Nov 2023target 2025
Hydro project 899609, Jackson County
Hydro
1.8 MWAgreement signed Jackson, NCSoutheast Jun 2023target 2026
Hydro project 899793, Jackson County
Hydro
1.5 MWAgreement signed Jackson, NCSoutheast Jun 2023target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)