United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Missouri, Southeast

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown275,999 MW
Active in queue5,999 MW27 requests
Agreement signed3,459 MW15 requests
Withdrawn449,276 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

27 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-83, Randolph County
Onshore wind
1,018 MWAgreement signed Randolph, MOSoutheast Jun 2019target 2027
Onshore wind project GI-122, Randolph County
Onshore wind
500 MWIn study Randolph, MOSoutheast May 2024target 2028
Gas project GI-132, Butler County
Gas
460 MWIn study Butler, MOSoutheast Jul 2025target 2030
Gas project GI-131, Randolph County
Gas
460 MWIn study Randolph, MOSoutheast Jul 2025target 2030
Gas project GI-126, Randolph County
Gas
460 MWIn study Randolph, MOSoutheast Jan 2025target 2029
Gas project GI-128, Clinton County
Gas
460 MWIn study Clinton, MOSoutheast Jul 2025target 2030
Gas project GI-121, Randolph County
Gas
460 MWAgreement signed Randolph, MOSoutheast May 2024target 2030
Gas project GI-101, Clinton County
Gas
460 MWAgreement signed Clinton, MOSoutheast Jul 2022target 2027
Onshore wind project GI-95, Dade County
Onshore wind
247 MWAgreement signed Dade, MOSoutheast Dec 2020target 2026
Solar project GI-120, Randolph County
Solar
245 MWAgreement signed Randolph, MOSoutheast Apr 2024target 2031
Onshore wind project GI-53, Nodaway County
Onshore wind
238 MWAgreement signed Nodaway, MOSoutheast May 2016target 2018
Onshore wind project GI-61, Nodaway County
Onshore wind
230 MWAgreement signed Nodaway, MOSoutheast May 2017target 2019
Solar project GI-86, Randolph County
Solar
100 MWAgreement signed Randolph, MOSoutheast Oct 2019target 2027
Solar project GI-93, Macon County
Solar
100 MWAgreement signed Macon, MOSoutheast Nov 2020target 2026
Solar project GI-90, Randolph County
Solar
100 MWAgreement signed Randolph, MOSoutheast Jul 2020target 2027
Solar project GI-91, Carroll County
Solar
96.0 MWAgreement signed Carroll, MOSoutheast Jul 2020target 2027
Solar project GI-127, Ralls County
Solar
80.0 MWIn study Ralls, MOSoutheast May 2025target 2028
Gas project GI-102, Clinton County
Gas
75.0 MWAgreement signed Clinton, MOSoutheast Jul 2022target 2027
Gas project GI-117, New Madrid County
Gas
46.0 MWAgreement signed New Madrid, MOSoutheast May 2023target 2024
Coal project GI-48, Randolph County
Coal
33.0 MWIn study Randolph, MOSoutheast Oct 2012target 2012
Coal project GI-43, Randolph County
Coal
28.2 MWIn study Randolph, MOSoutheast Nov 2009target 2012
Gas project GI-116, New Madrid County
Gas
26.0 MWAgreement signed New Madrid, MOSoutheast May 2023target 2024
Coal project GI-40, New Madrid County
Coal
20.0 MWIn study New Madrid, MOSoutheast Oct 2009target 2011
Coal project GI-39, New Madrid County
Coal
20.0 MWIn study New Madrid, MOSoutheast Oct 2009target 2011
Onshore wind project GI-60, Gentry County
Onshore wind
18.0 MWAgreement signed Gentry, MOSoutheast Apr 2017
Coal project GI-41, Randolph County
Coal
17.0 MWIn study Randolph, MOSoutheast Oct 2009target 2012
Coal project GI-42, Randolph County
Coal
1.7 MWIn study Randolph, MOSoutheast Nov 2009target 2010

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)