United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Queue requests in study in SPP (Southwest Power Pool) (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown255,570 MW
Active in queue9,029 MW44 requests
Agreement signed3,459 MW19 requests
Withdrawn7013.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

25 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2021-030, Linn County
Solar
510 MWIn study Linn, KSSPP May 2021target 2026
Onshore wind project GEN-2021-070, Hodgeman County
Onshore wind
504 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Solar project GEN-2021-096, Coffey County
Solar
500 MWIn study Coffey, KSSPP Apr 2021target 2027
Solar + storage project GEN-2021-090, Yoakum County
Solar + storage
400 MWIn study Yoakum, TXSPP Apr 2021target 2028
Onshore wind project GEN-2021-057, Antelope County
Onshore wind
300 MWIn study Antelope, NESPP Apr 2021target 2027
Battery storage project GEN-2021-006, Labette County
Battery storage
300 MWIn study Labette, KSSPP May 2021target 2026
Battery storage project GEN-2021-029, Linn County
Battery storage
254 MWIn study Linn, KSSPP May 2021target 2026
Onshore wind project GEN-2021-016, Johnston County
Onshore wind
250 MWIn study Johnston, OKSPP Apr 2021target 2029
Onshore wind project GEN-2021-069, Hodgeman County
Onshore wind
250 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Onshore wind project GEN-2021-068, Hodgeman County
Onshore wind
250 MWIn study Hodgeman, KSSPP Apr 2021target 2027
Onshore wind project GEN-2021-025, Woodward County
Onshore wind
203 MWIn study Woodward, OKSPP May 2021target 2026
Solar project GEN-2021-107, Pottawatomie County
Solar
202 MWIn study Pottawatomie, KSSPP May 2021target 2026
Battery storage project GEN-2021-040, Cass County
Battery storage
200 MWIn study Cass, NESPP Apr 2021target 2029
Battery storage project GEN-2021-038, Titus County
Battery storage
200 MWIn study Titus, TXSPP Apr 2021target 2028
Solar project GEN-2021-108, Cass County
Solar
182 MWIn study Cass, NESPP May 20212025
Solar + storage project GEN-2021-063, Mccurtain County
Solar + storage
155 MWIn study Mccurtain, OKSPP Apr 2021target 2027
Onshore wind project GEN-2021-021, Stevens County
Onshore wind
150 MWIn study Stevens, KSSPP Apr 2021target 2027
Solar project GEN-2021-076, Ellis County
Solar
113 MWIn study Ellis, KSSPP May 2021target 2026
Solar project GEN-2021-035, Grant County
Solar
113 MWIn study Grant, KSSPP May 2021target 2026
Solar project GEN-2021-027, Lancaster County
Solar
102 MWIn study Lancaster, NESPP May 2021target 2026
Solar + storage project GEN-2021-064, Caddo County
Solar + storage
100 MWIn study Caddo, OKSPP Apr 2021target 2028
Battery storage project GEN-2021-039, Douglas County
Battery storage
100 MWIn study Douglas, NESPP Apr 2021target 2030
Battery storage project GEN-2021-088, Cleveland County
Battery storage
100 MWIn study Cleveland, OKSPP Apr 2021target 2027
Solar + storage project GEN-2021-077, Pettis County
Solar + storage
95.0 MWIn study Pettis, MOSPP Apr 2021target 2027
Onshore wind project GEN-2021-017, Cloud County
Onshore wind
37.5 MWIn study Cloud, KSSPP Apr 2021target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)