Projects with signed interconnection agreements in SPP (Southwest Power Pool) (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown193,459 MW
Active in queue9,029 MW44 requests
Agreement signed3,459 MW19 requests
Withdrawn7013.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

19 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project GEN-2021-005, Saline County
Battery storage
350 MWAgreement signed Saline, KSSPP May 2021target 2030
Solar project GEN-2021-023, Grant County
Solar
306 MWAgreement signed Grant, KSSPP May 2021target 2030
Solar project GEN-2021-053, Muskogee County
Solar
300 MWAgreement signed Muskogee, OKSPP Apr 2021target 2031
Onshore wind project GEN-2021-056, Harper County
Onshore wind
300 MWAgreement signed Harper, KSSPP Apr 2021target 2030
Battery storage project GEN-2021-043, Lancaster County
Battery storage
250 MWAgreement signed Lancaster, NESPP Apr 2021target 2030
Solar project GEN-2021-047, Mayes County
Solar
250 MWAgreement signed Mayes, OKSPP Apr 2021target 2029
Solar project GEN-2021-018, Noble County
Solar
231 MWAgreement signed Noble, OKSPP Apr 2021target 2028
Solar project GEN-2021-049, Lancaster County
Solar
225 MWAgreement signed Lancaster, NESPP Apr 2021target 2029
Solar project GEN-2021-033, Franklin County
Solar
204 MWAgreement signed Franklin, ARSPP May 2021target 2028
Solar project GEN-2021-036, Little River County
Solar
204 MWAgreement signed Little River, ARSPP May 2021target 2027
Solar project GEN-2021-101, Douglas County
Solar
159 MWAgreement signed Douglas, KSSPP May 2021target 2027
Battery storage project GEN-2021-103, Johnson County
Battery storage
150 MWAgreement signed Johnson, KSSPP May 2021target 2030
Solar project GEN-2021-034, Lancaster County
Solar
113 MWAgreement signed Lancaster, NESPP May 2021target 2030
Battery storage project GEN-2021-041, Canadian County
Battery storage
100 MWAgreement signed Canadian, OKSPP Apr 2021target 2027
Battery storage project GEN-2021-052, Muskogee County
Battery storage
75.0 MWAgreement signed Muskogee, OKSPP Apr 2021target 2031
Battery storage project GEN-2021-048, Lancaster County
Battery storage
75.0 MWAgreement signed Lancaster, NESPP Apr 2021target 2029
Battery storage project GEN-2021-019, Noble County
Battery storage
74.9 MWAgreement signed Noble, OKSPP Apr 2021target 2028
Battery storage project GEN-2021-042, Jackson County
Battery storage
50.0 MWAgreement signed Jackson, MOSPP Apr 2021target 2028
Solar project GEN-2021-SR8, Harper County
Solar
42.0 MWAgreement signed Harper, KSSPP May 20212023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)