πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Kentucky

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in Kentucky, PJM (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6722 MW
Active in queue722 MW6 requests
Agreement signed722 MW6 requests
Withdrawn332,409 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Goldfinch Solar
Solar Β· Goldfinch Solar, LLC
250 MWAgreement signed Mason, KYPJM Feb 2020target 2030
Exie Solar
Solar Β· Exie Solar, LLC
150 MWAgreement signed Green, KYPJM Sep 2020target 2028
Summer Shade Solar
Solar + storage Β· Summer Shade Solar, LLC
106 MWAgreement signed Metcalfe, KYPJM Sep 2020target 2028
Stonecrop Solar
Solar Β· CPV Stonecrop Solar, LLC
82.0 MWAgreement signed Hardin, KYPJM Sep 2020target 2029
Bright Mountain Solar
Solar
80.0 MWAgreement signed Perry, KYPJM Jul 2020target 2027
Barrelhead
Solar Β· Barrelhead Solar, LLC
54.0 MWAgreement signed KYPJM Sep 2020target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)