United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in NYISO (New York) (2020 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Vineyard Wind I Offshore wind · OCS-A 0522, LLC |
1,403 MW | Withdrawn / abandoned |
| Vineyard Wind II Offshore wind · OCS-A 0522, LLC |
1,403 MW | Withdrawn / abandoned |
| NY Wind - New Bridge Road Offshore wind · Bay State Wind |
1,325 MW | Withdrawn / abandoned |
| EI Steinway 2 Offshore wind · Beacon Wind LLC |
1,300 MW | Withdrawn / abandoned |
| EI Steinway 1 Offshore wind · Beacon Wind LLC |
1,300 MW | Withdrawn / abandoned |
| EI East Shoreham Offshore wind · Beacon Wind LLC |
1,300 MW | Withdrawn / abandoned |
| EI Glenwood Landing Offshore wind · Beacon Wind LLC |
1,300 MW | Withdrawn / abandoned |
| EI Fort Salonga Offshore wind · Beacon Wind LLC |
1,300 MW | Withdrawn / abandoned |
| NY Wind - Pilgrim Offshore wind · Bay State Wind |
1,276 MW | Withdrawn / abandoned |
| NY Wind - Mott Haven Offshore wind · Bay State Wind |
1,272 MW | Withdrawn / abandoned |
| NY Wind - Shore Road Offshore wind · Bay State Wind |
1,272 MW | Withdrawn / abandoned |
| Attentive Energy Offshore wind · Attentive Energy LLC |
1,200 MW | Withdrawn / abandoned |
| NY Wind Holbrook 2 Uprate Offshore wind · Sunrise Wind LCC |
1,050 MW | Withdrawn / abandoned |
| NY Hydro-Kinetic Project 1 Hydro · Hydroelectric Corporation |
550 MW | Withdrawn / abandoned |
| Oyster Shore BESS Battery storage · Juno Power Management LLC |
500 MW | Withdrawn / abandoned |
| Buchanan Point BESS II Battery storage · Juno Power Management LLC |
500 MW | Withdrawn / abandoned |
| Cuomo Hydro 1 Battery storage · Renewable Energy Aggregators, Inc. |
300 MW | Withdrawn / abandoned |
| Egc BESS Battery storage · Juno Power Management LLC |
300 MW | Withdrawn / abandoned |
| Declaration Energy Center Solar · Declaration Energy Center, LLC |
300 MW | Withdrawn / abandoned |
| Tremont BESS Battery storage · Juno Power Management LLC |
300 MW | Withdrawn / abandoned |
| Mifflin Solar + storage · Renewable Energy Aggregators, Inc. |
300 MW | Withdrawn / abandoned |
| Cuomo Hydro 2 Battery storage · Renewable Energy Aggregators, Inc. |
300 MW | Withdrawn / abandoned |
| Buchanan Point BESS III Battery storage · Juno Power Management LLC |
300 MW | Withdrawn / abandoned |
| Buchanan Point BESS Battery storage · Juno Power Management LLC |
300 MW | Withdrawn / abandoned |
| Wildwood-Riverhead Energy Storage Battery storage · Wildwood Energy Storage, LLC |
298 MW | Withdrawn / abandoned |
| Cayuga Solar Solar · sPower Development Company, LLC |
207 MW | Withdrawn / abandoned |
| Barrett Energy Storage Center Battery storage · Island Park Energy Center, LLC |
200 MW | Withdrawn / abandoned |
| Riverline Energy Center Battery storage · Riverline Energy Center, LLC |
200 MW | Withdrawn / abandoned |
| Harvest Hills Solar Solar + storage · ConnectGen Cayuga County LLC |
200 MW | Withdrawn / abandoned |
| Silverline Energy Center Solar + storage · Silverline Energy Center, LLC |
150 MW | Withdrawn / abandoned |
| Holtsville Energy Center Battery storage · Clean Energy Generation, LLC |
150 MW | Withdrawn / abandoned |
| Holbrook Energy Center Battery storage · Clean Energy Generation, LLC |
150 MW | Withdrawn / abandoned |
| NY Kinetic Plant 1 Hydro · Hydroelectric Corporation |
144 MW | Withdrawn / abandoned |
| Mainesburg ESS Battery storage · Juno Power Management LLC |
130 MW | Withdrawn / abandoned |
| Hicksville Storage Battery storage · Juno Power Management LLC |
125 MW | Withdrawn / abandoned |
| Addison Solar Solar · SWEB Development USA LLC |
120 MW | Withdrawn / abandoned |
| Rutland Center Solar Solar · Rutland Center Solar 1, LLC |
110 MW | Withdrawn / abandoned |
| Thousand Island Solar Solar · Cypress Creek Renewables, LLC |
110 MW | Withdrawn / abandoned |
| Bangor Solar Solar · SWEB Development USA, LLC |
107 MW | Withdrawn / abandoned |
| Fort Edward Solar Farm (NY53) Solar · Fort Edward Solar LLC |
100 MW | Withdrawn / abandoned |
| Alfred Oaks Solar Solar + storage · Northland Power U.S. Projects |
100 MW | Withdrawn / abandoned |
| Worth Wind Onshore wind · SWEB Development USA, LLC |
92.0 MW | Withdrawn / abandoned |
| Kce NY 22 Battery storage · KCE NY 22, LLC |
90.0 MW | Withdrawn / abandoned |
| Birdie Energy Storage Battery storage · Birdie Energy Storage, LLC |
83.0 MW | Withdrawn / abandoned |
| Honey Ridge Solar Solar · Honey Ridge Solar 1 |
80.0 MW | Withdrawn / abandoned |
| Kce NY 19 Battery storage · KCE NY 19 LLC |
80.0 MW | Withdrawn / abandoned |
| NYC Energy BNY Phase 1 Battery storage · NYC Energy |
79.9 MW | Withdrawn / abandoned |
| Suffolk BESS Battery storage · Suffolk BESS LLC |
79.7 MW | Withdrawn / abandoned |
| Suffolk County Storage II Battery storage · Suffolk County Energy Storage II |
76.8 MW | Withdrawn / abandoned |
| Kce NY 26 Battery storage · KCE NY 26, LLC |
60.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- PJM (Mid-Atlantic, Midwest)719 · 47.9 GW
- CAISO (California)107 · 46.6 GW
- West (non-ISO utilities)184 · 38.3 GW
- Southeast (non-ISO utilities)178 · 30.1 GW
- MISO (Midcontinent)195 · 27.2 GW
- NYISO (New York)129 · 25.5 GW
- SPP (Southwest Power Pool)60 · 10.4 GW
- ERCOT (Texas)67 · 10.4 GW
- ISO-NE (New England)113 · 9,841 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)