Battery storage interconnection queue in MISO (Midcontinent)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown30555.0 GW
Active in queue55.0 GW305 requests
Agreement signed1,131 MW14 requests
Withdrawn40350.6 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

305 requests ยท page 1 of 7
ProjectCapacityStatusLocationRegionQueuedOnline
Malden BESS
Battery storage ยท NIPSCO
630 MWIn study Porter, INMISO Aug 2025target 2027
Mitchell BESS
Battery storage ยท NIPSCO
527 MWIn study Lake, INMISO Aug 2025target 2028
Battery storage project J4072, Redwood County
Battery storage
500 MWIn study Redwood, MNMISO Oct 2025target 2028
Battery storage project J4078, Mower County
Battery storage
500 MWIn study Mower, MNMISO Oct 2025target 2030
Battery storage project J2590, Huron County
Battery storage
500 MWIn study Huron, MIMISO Sep 2022target 2025
Battery storage project J4194, Meeker County
Battery storage
500 MWIn study Meeker, MNMISO Oct 2025target 2028
Battery storage project J4100, Livingston Parish County
Battery storage
500 MWIn study Livingston Parish, LAMISO Oct 2025target 2030
Battery storage project J4082, Jefferson County
Battery storage
500 MWIn study Jefferson, ARMISO Oct 2025target 2030
Monroe ERAS
Battery storage ยท DTE Electric
432 MWIn study Monroe, MIMISO Aug 2025target 2028
Battery storage project J2496, White County
Battery storage
400 MWIn study White, INMISO Sep 2022target 2026
Battery storage project J4076, Jefferson Davis Parish County
Battery storage
400 MWIn study Jefferson Davis Parish, LAMISO Oct 2025target 2030
Battery storage project J2304, Columbia County
Battery storage
400 MWIn study Columbia, WIMISO Dec 2021target 2024
Battery storage project J4093, Mason County
Battery storage
400 MWIn study Mason, MIMISO Oct 2025target 2030
Battery storage project J3992, Eaton County
Battery storage
400 MWIn study Eaton, MIMISO Apr 2025target 2028
Battery storage project J3994, Monroe County
Battery storage
360 MWIn study Monroe, MIMISO Apr 2025target 2028
Battery storage project J3872, Wayne County
Battery storage
350 MWIn study Wayne, MIMISO Jan 2025target 2029
Battery storage project J4168, Goodhue County
Battery storage
330 MWIn study Goodhue, MNMISO Oct 2025target 2028
Nobles BESS
Battery storage ยท Xcel Energy
314 MWIn study Nobles, MNMISO Aug 2025target 2028
Sherco South BESS
Battery storage ยท Xcel Energy
314 MWIn study Sherburne, MNMISO Aug 2025target 2027
Benton Energy Storage II
Battery storage ยท Xcel Energy
310 MWIn study Benton, MNMISO Aug 2025target 2028
Brickyard Energy Storage
Battery storage ยท Brickyard Energy Storge, LLC
310 MWIn study Boone, INMISO Aug 2025target 2028
Battery storage project J2469, Linn County
Battery storage
300 MWIn study Linn, IAMISO Sep 2022target 2027
Battery storage project J3006, Milwaukee County
Battery storage
300 MWIn study Milwaukee, WIMISO Jul 2025target 2028
Battery storage project J3840, St. Landry Parish County
Battery storage
300 MWIn study St. Landry Parish, LAMISO Dec 2024target 2030
Battery storage project J2716, Dakota County
Battery storage
300 MWIn study Dakota, MNMISO Sep 2022target 2027
Battery storage project J3946, Tazewell County
Battery storage
300 MWIn study Tazewell, ILMISO Mar 2025target 2030
Battery storage project J3518, Gasconade County
Battery storage
300 MWIn study Gasconade, MOMISO Apr 2024target 2028
Battery storage project J4095, Huron County
Battery storage
300 MWIn study Huron, MIMISO Oct 2025target 2030
Battery storage project J2377, Peoria County
Battery storage
300 MWIn study Peoria, ILMISO Nov 2024target 2028
Battery storage project J4016, Tuscola County
Battery storage
300 MWIn study Tuscola, MIMISO May 2025target 2029
Battery storage project J2647, Franklin County
Battery storage
300 MWIn study Franklin, ILMISO Sep 2022target 2028
Battery storage project J2215, Lake County
Battery storage
300 MWIn study Lake, INMISO Mar 2022target 2024
Battery storage project J4094, Huron County
Battery storage
300 MWIn study Huron, MIMISO Oct 2025target 2030
Battery storage project J3558, Champaign County
Battery storage
300 MWIn study Champaign, ILMISO Apr 2024target 2027
Battery storage project J3525, Rock Island County
Battery storage
300 MWIn study Rock Island, ILMISO Apr 2024target 2028
Battery storage project J3834, Gibson County
Battery storage
300 MWIn study Gibson, INMISO Sep 2024target 2026
Battery storage project J4098, Lafayette Parish County
Battery storage
300 MWIn study Lafayette Parish, LAMISO Oct 2025target 2030
Battery storage project J4075, St. Landry Parish County
Battery storage
300 MWIn study St. Landry Parish, LAMISO Oct 2025target 2030
Battery storage project J3216, Peoria County
Battery storage
300 MWIn study Peoria, ILMISO Sep 2022target 2027
Battery storage project J3417, Macon County
Battery storage
300 MWIn study Macon, ILMISO Apr 2024target 2028
Battery storage project J2423, Columbia County
Battery storage
300 MWIn study Columbia, WIMISO Sep 2022target 2027
Battery storage project E0017, Lincoln County
Battery storage ยท Union Electric Company d/b/a Ameren Missouri
258 MWIn study Lincoln, MOMISO Aug 2025target 2028
Battery storage project J3836, Eaton County
Battery storage
250 MWIn study Eaton, MIMISO Oct 2024target 2028
Battery storage project J4167, Allegan County
Battery storage
250 MWIn study Allegan, MIMISO Sep 2025target 2030
Battery storage project J3845, Monroe County
Battery storage
250 MWIn study Monroe, MIMISO Nov 2024target 2029
Battery storage project J2628, Huron County
Battery storage
250 MWIn study Huron, MIMISO Sep 2022target 2028
Battery storage project J3883, Crawford County
Battery storage
250 MWIn study Crawford, ILMISO Feb 2025target 2030
Battery storage project J4198, Christian County
Battery storage
250 MWIn study Christian, ILMISO Sep 2025target 2030
Battery storage project J4153, Grant County
Battery storage
250 MWIn study Grant, SDMISO Oct 2025target 2030
Battery storage project J4089, Freeborn County
Battery storage
250 MWIn study Freeborn, MNMISO Oct 2025target 2029
Page 1 of 7

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)