Malden BESS Battery storage ยท NIPSCO |
630 MW | In study |
Porter, IN | MISO |
Aug 2025 | target 2027 |
Mitchell BESS Battery storage ยท NIPSCO |
527 MW | In study |
Lake, IN | MISO |
Aug 2025 | target 2028 |
Battery storage project J4072, Redwood County Battery storage |
500 MW | In study |
Redwood, MN | MISO |
Oct 2025 | target 2028 |
Battery storage project J4078, Mower County Battery storage |
500 MW | In study |
Mower, MN | MISO |
Oct 2025 | target 2030 |
Battery storage project J2590, Huron County Battery storage |
500 MW | In study |
Huron, MI | MISO |
Sep 2022 | target 2025 |
Battery storage project J4194, Meeker County Battery storage |
500 MW | In study |
Meeker, MN | MISO |
Oct 2025 | target 2028 |
Battery storage project J4100, Livingston Parish County Battery storage |
500 MW | In study |
Livingston Parish, LA | MISO |
Oct 2025 | target 2030 |
Battery storage project J4082, Jefferson County Battery storage |
500 MW | In study |
Jefferson, AR | MISO |
Oct 2025 | target 2030 |
Monroe ERAS Battery storage ยท DTE Electric |
432 MW | In study |
Monroe, MI | MISO |
Aug 2025 | target 2028 |
Battery storage project J2496, White County Battery storage |
400 MW | In study |
White, IN | MISO |
Sep 2022 | target 2026 |
Battery storage project J4076, Jefferson Davis Parish County Battery storage |
400 MW | In study |
Jefferson Davis Parish, LA | MISO |
Oct 2025 | target 2030 |
Battery storage project J2304, Columbia County Battery storage |
400 MW | In study |
Columbia, WI | MISO |
Dec 2021 | target 2024 |
Battery storage project J4093, Mason County Battery storage |
400 MW | In study |
Mason, MI | MISO |
Oct 2025 | target 2030 |
Battery storage project J3992, Eaton County Battery storage |
400 MW | In study |
Eaton, MI | MISO |
Apr 2025 | target 2028 |
Battery storage project J3994, Monroe County Battery storage |
360 MW | In study |
Monroe, MI | MISO |
Apr 2025 | target 2028 |
Battery storage project J3872, Wayne County Battery storage |
350 MW | In study |
Wayne, MI | MISO |
Jan 2025 | target 2029 |
Battery storage project J4168, Goodhue County Battery storage |
330 MW | In study |
Goodhue, MN | MISO |
Oct 2025 | target 2028 |
Nobles BESS Battery storage ยท Xcel Energy |
314 MW | In study |
Nobles, MN | MISO |
Aug 2025 | target 2028 |
Sherco South BESS Battery storage ยท Xcel Energy |
314 MW | In study |
Sherburne, MN | MISO |
Aug 2025 | target 2027 |
Benton Energy Storage II Battery storage ยท Xcel Energy |
310 MW | In study |
Benton, MN | MISO |
Aug 2025 | target 2028 |
Brickyard Energy Storage Battery storage ยท Brickyard Energy Storge, LLC |
310 MW | In study |
Boone, IN | MISO |
Aug 2025 | target 2028 |
Battery storage project J2469, Linn County Battery storage |
300 MW | In study |
Linn, IA | MISO |
Sep 2022 | target 2027 |
Battery storage project J3006, Milwaukee County Battery storage |
300 MW | In study |
Milwaukee, WI | MISO |
Jul 2025 | target 2028 |
Battery storage project J3840, St. Landry Parish County Battery storage |
300 MW | In study |
St. Landry Parish, LA | MISO |
Dec 2024 | target 2030 |
Battery storage project J2716, Dakota County Battery storage |
300 MW | In study |
Dakota, MN | MISO |
Sep 2022 | target 2027 |
Battery storage project J3946, Tazewell County Battery storage |
300 MW | In study |
Tazewell, IL | MISO |
Mar 2025 | target 2030 |
Battery storage project J3518, Gasconade County Battery storage |
300 MW | In study |
Gasconade, MO | MISO |
Apr 2024 | target 2028 |
Battery storage project J4095, Huron County Battery storage |
300 MW | In study |
Huron, MI | MISO |
Oct 2025 | target 2030 |
Battery storage project J2377, Peoria County Battery storage |
300 MW | In study |
Peoria, IL | MISO |
Nov 2024 | target 2028 |
Battery storage project J4016, Tuscola County Battery storage |
300 MW | In study |
Tuscola, MI | MISO |
May 2025 | target 2029 |
Battery storage project J2647, Franklin County Battery storage |
300 MW | In study |
Franklin, IL | MISO |
Sep 2022 | target 2028 |
Battery storage project J2215, Lake County Battery storage |
300 MW | In study |
Lake, IN | MISO |
Mar 2022 | target 2024 |
Battery storage project J4094, Huron County Battery storage |
300 MW | In study |
Huron, MI | MISO |
Oct 2025 | target 2030 |
Battery storage project J3558, Champaign County Battery storage |
300 MW | In study |
Champaign, IL | MISO |
Apr 2024 | target 2027 |
Battery storage project J3525, Rock Island County Battery storage |
300 MW | In study |
Rock Island, IL | MISO |
Apr 2024 | target 2028 |
Battery storage project J3834, Gibson County Battery storage |
300 MW | In study |
Gibson, IN | MISO |
Sep 2024 | target 2026 |
Battery storage project J4098, Lafayette Parish County Battery storage |
300 MW | In study |
Lafayette Parish, LA | MISO |
Oct 2025 | target 2030 |
Battery storage project J4075, St. Landry Parish County Battery storage |
300 MW | In study |
St. Landry Parish, LA | MISO |
Oct 2025 | target 2030 |
Battery storage project J3216, Peoria County Battery storage |
300 MW | In study |
Peoria, IL | MISO |
Sep 2022 | target 2027 |
Battery storage project J3417, Macon County Battery storage |
300 MW | In study |
Macon, IL | MISO |
Apr 2024 | target 2028 |
Battery storage project J2423, Columbia County Battery storage |
300 MW | In study |
Columbia, WI | MISO |
Sep 2022 | target 2027 |
Battery storage project E0017, Lincoln County Battery storage ยท Union Electric Company d/b/a Ameren Missouri |
258 MW | In study |
Lincoln, MO | MISO |
Aug 2025 | target 2028 |
Battery storage project J3836, Eaton County Battery storage |
250 MW | In study |
Eaton, MI | MISO |
Oct 2024 | target 2028 |
Battery storage project J4167, Allegan County Battery storage |
250 MW | In study |
Allegan, MI | MISO |
Sep 2025 | target 2030 |
Battery storage project J3845, Monroe County Battery storage |
250 MW | In study |
Monroe, MI | MISO |
Nov 2024 | target 2029 |
Battery storage project J2628, Huron County Battery storage |
250 MW | In study |
Huron, MI | MISO |
Sep 2022 | target 2028 |
Battery storage project J3883, Crawford County Battery storage |
250 MW | In study |
Crawford, IL | MISO |
Feb 2025 | target 2030 |
Battery storage project J4198, Christian County Battery storage |
250 MW | In study |
Christian, IL | MISO |
Sep 2025 | target 2030 |
Battery storage project J4153, Grant County Battery storage |
250 MW | In study |
Grant, SD | MISO |
Oct 2025 | target 2030 |
Battery storage project J4089, Freeborn County Battery storage |
250 MW | In study |
Freeborn, MN | MISO |
Oct 2025 | target 2029 |