United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in MISO (Midcontinent) (2012 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Gas project J259, Shelby County Gas |
1,065 MW | Withdrawn / abandoned |
| Gas project J250, Shelby County Gas |
999 MW | Withdrawn / abandoned |
| Gas project J244, Christian County Gas |
726 MW | Withdrawn / abandoned |
| Gas project J240, Vermillion County Gas |
720 MW | Withdrawn / abandoned |
| Gas project J248, Outagamie County Gas |
675 MW | Withdrawn / abandoned |
| Onshore wind project MPC02600, Mclean County Onshore wind |
400 MW | Withdrawn / abandoned |
| Onshore wind project J266, Roberts County Onshore wind |
200 MW | Withdrawn / abandoned |
| Coal project J239, Morgan County Coal |
200 MW | Withdrawn / abandoned |
| Onshore wind project J254, Lyon County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J107, Logan County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J247, Sanilac County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J257, Newton County Onshore wind |
150 MW | Withdrawn / abandoned |
| Onshore wind project J264, Shiawassee County Onshore wind |
121 MW | Withdrawn / abandoned |
| Onshore wind project J260, Ford County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project J265, Marshall County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project J261, Montgomery County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project J245, Tuscola County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project J243, Jackson County Onshore wind |
75.0 MW | Withdrawn / abandoned |
| Onshore wind project J253, Woodbury County Onshore wind |
48.3 MW | Withdrawn / abandoned |
| Onshore wind project J252, Audubon County Onshore wind |
39.1 MW | Withdrawn / abandoned |
| Onshore wind project J251, Ramsey County Onshore wind |
27.5 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- PJM (Mid-Atlantic, Midwest)111 Β· 19.3 GW
- CAISO (California)60 Β· 12.3 GW
- West (non-ISO utilities)95 Β· 9,460 MW
- Southeast (non-ISO utilities)36 Β· 9,047 MW
- ERCOT (Texas)24 Β· 6,711 MW
- MISO (Midcontinent)21 Β· 6,395 MW
- SPP (Southwest Power Pool)30 Β· 4,307 MW
- NYISO (New York)10 Β· 1,963 MW
- ISO-NE (New England)10 Β· 996 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)